Data Centres Queue to Enter Indonesia, Requiring a Huge 30,000 Megawatts of Power
Jakarta, CNBC Indonesia — PT PLN (Persero) has recorded a surge in foreign investment in data centres entering Indonesia, with requests for power supply reaching 30 gigawatts (GW). The company is preparing a strategy to accommodate the major increase in electricity demand without disrupting the reliability of the national system.
PLN President Director Suroso Isnandar estimates that electricity subsidies for data centre projects in Indonesia could reach Rp 8 trillion this year.
“Now, look at the data centre waiting list: 30 GW, or 30,000 MW,” Suroso said at the 2026 National Energy Forum in Jakarta, according to a report on Thursday (26 November 2026).
“Electricity subsidies for data centres this year alone have reached Rp 8 trillion. That is why so many data centres are moving to Indonesia. The waiting list has now reached 30 GW, or 30,000 MW,” he added.
Suroso explained that investment in Indonesian data centres has grown amid restrictions on energy consumption and cooling water in neighbouring countries such as Singapore and Malaysia.
“So why are data centres coming to Indonesia in large numbers? Because they have already been turned away elsewhere. For example, some moved from Singapore to Johor Bahru. In Johor Bahru, calculations showed that the amount of water they use to cool data centres exceeds the water needed to irrigate their oil palm plantations,” he said.
To respond to this demand, PLN is applying a phased service scheme. For initial projects with a capacity of 100–300 megawatts (MW), the utility says it can provide electricity directly from its main grid.
“PLN’s general strategy is to accept the first phase, because the initial stage of a data centre typically requires only 100 MW, 200 MW or 300 MW—within our reach,” Suroso said.
For larger developments, however, PLN will require developers to invest jointly or build their own power plants.
“But if they move on to the next stage, especially if they reach gigawatt scale, we will need to discuss co-investment. If necessary, the data centre must build its own power plant, or captive power,” Suroso said.
Source: jawawa.id (https://jawawa.id/newsitem/data-centres-queue-to-enter-indonesia-requiring-a-huge-30-000-megawatts-of-power-1795683102)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20261126133959-4-788734/data-center-antre-masuk-ri-butuh-listrik-jumbo-30000-mega-watt), translated from Indonesian