Coordinating Minister for Food Affairs inspects Bali waste-to-energy plant, now 26 per cent complete

| Source: Antara (Indonesian) Translated from Indonesian | Infrastructure
Coordinating Minister for Food Affairs inspects Bali waste-to-energy plant, now 26 per cent complete
Image: Antara (Indonesian)

Denpasar (ANTARA) – Coordinating Minister for Food Affairs Zulkifli Hasan has inspected construction of a waste-to-energy (PSEL) facility in Bali, where progress has exceeded 26 per cent.

“This is the third PSEL facility, and the one in Bali is already more than 26 per cent complete,” Zulkifli Hasan said during the inspection in Denpasar on Wednesday.

Construction of the Bali PSEL project began with a groundbreaking ceremony on 8 July 2026. It is designed to process waste, particularly from Denpasar and Badung regency.

Zulkifli said he had conducted the site visit to verify that the emergency waste-management policy was being implemented on the ground.

He said the PSEL facility in Palembang, which was completed on 8 December, would be inaugurated after commissioning. After inspecting the Bali site, he also scheduled visits to Bogor, Bekasi City and other areas, including Bantar Gebang.

The government aims to complete construction of the Bali PSEL facility in 2027, with the plant expected to be operational by December that year.

Overall, Zulkifli said the government aimed to resolve the waste emergency in various regions between 2027 and 2028.

More from 25 November 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/coordinating-minister-for-food-affairs-inspects-bali-waste-to-energy-plant-now-26-per-cent-complete-1795604131)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5877779/menko-pangan-tinjau-psel-bali-dengan-progres-26-persen), translated from Indonesian
Print