Coordinating Minister Decree Mandates Task Force to Oversee Budget and Recovery Hurdles in Sumatra

| Source: Tempo (Indonesian) Translated from Indonesian | Infrastructure

The Decree of the Coordinating Minister for Human Development and Cultural Affairs (Menko PMK) Number 25 of 2026 regarding the Master Plan for the Accelerated Rehabilitation and Reconstruction of Post-Disaster Sumatra does more than just establish a roadmap for recovering areas affected by flash floods and landslides in Aceh, North Sumatra, and West Sumatra. The document also regulates the mechanisms for supervision, evaluation, and periodic reporting of rehabilitation and reconstruction efforts to the President.

Signed by the Coordinating Minister on 13 May 2026, this decree serves as the foundation for permanent rehabilitation and reconstruction efforts lasting until 2028. The government is utilising the Sumatra PRRP Master Plan as a national reference to synchronise programmes across ministries, agencies, and local governments, as well as to prepare the necessary financing for post-disaster recovery.

The decree contains ten points that mandate the Task Force for the Acceleration of Rehabilitation and Reconstruction (Satgas PRR) in executing the recovery process. The first two points establish the Master Plan as the national benchmark for post-disaster rehabilitation and reconstruction in Sumatra.

Subsequent points require 32 ministries, agencies, and local governments in the three affected provinces to adhere to the Sumatra PRRP Master Plan. The government maintains that large-scale post-disaster recovery cannot be conducted in a sectoral or fragmented manner, but requires a single, integrated national roadmap.

This Master Plan is effective for three years, from 2026 to 2028. Additionally, the PRR Task Force is tasked with monitoring and evaluating programme targets, implementation, budget usage, policies, and various obstacles encountered in the field.

This oversight has already been implemented by the PRR Task Force during its operations in Sumatra. For instance, from 28 May to 2 June, the team monitored the construction of bridges and embankments in six regions in Aceh, coordinating with local governments to find effective solutions.

The results of these activities and evaluations will be reported by the Chairperson of the PRR Task Force Steering Committee to President Prabowo Subianto on a regular basis every two months, or at specific times as required.

Funding for rehabilitation and reconstruction may be sourced from the State Budget (APBN), Regional Budget (APBD), and other legitimate and non-binding funding sources.

In the Master Plan document, the government estimates that the total requirement for post-disaster rehabilitation and reconstruction in Sumatra reaches approximately Rp 205.2 trillion. The government aims for permanent rehabilitation and reconstruction to proceed gradually until 2028, with cross-ministerial and agency supervision to ensure programmes remain targeted and accountable.

The Master Plan includes 11,512 rehabilitation and reconstruction activities to be implemented in stages until 2028. These programmes encompass the construction of permanent housing, the rehabilitation of schools and health facilities, the construction of permanent roads and bridges, river normalisation, the rehabilitation of landslide-affected areas, and the economic recovery of communities through support for MSMEs, fishermen, and local markets.

The government is also adopting the ‘Build Back Better, Safer, and Sustainable’ (BBBSS) approach, which involves rebuilding to higher standards of safety, resilience, and sustainability. This concept is applied to housing construction, public infrastructure rehabilitation, the management of disaster-prone areas, and the environmental rehabilitation of upstream river regions.

Regarding the development of the Master Plan, the process began in February 202<0xE2><0x80><0x89>6, involving the Sumatra PRRP Task Force, the Coordinating Ministry for Human Development and Cultural Affairs, and 32 involved ministries and agencies. The document underwent several revisions and harmonisations between March and April before being finalised and signed by the Coordinating Minister on 13 May 2026.

Subsequently, on 25 May 2026, the government presented the Master Plan document for discussion with the House of Representatives (DPR) and the Minister of Finance as part of the synchronisation of budget support for permanent rehabilitation and reconstruction.

The Chairperson of the Sumatra PRRP Task Force and Minister of Home Affairs, Tito Karnavian, stated that the Master Plan is the key element of the permanent recovery phase in Sumatra following the emergency response and transition periods. “We are now moving towards the permanent recovery process, and this Master Plan is the key,” he said.

More from 9 June 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/coordinating-minister-decree-mandates-task-force-to-oversee-budget-and-recovery-hurdles-in-sumatra-1781017603)
Originally published by Tempo (Indonesian) (https://nasional.tempo.co/read/2107673/sk-menko-pmk-minta-satgas-prrp-awasi-anggaran-dan-kendala-pemulihan-di-lapangan), translated from Indonesian