Construction of Merah Putih Village Cooperative in Cipenjo Stalls, Dudung: There Was a Changeover at the Kodim
Image: Republika

The Chief of Staff to the President, Dudung Abdurachman, conducted a surprise inspection of the Merah Putih Village Cooperative (KDMP) in Cipenjo Village, Cileungsi, Bogor Regency, West Java, on Thursday (25/6), urging the acceleration of the construction completion.

According to a statement from the Office of the President (KSP) received in Jakarta on Friday, the inspection was carried out to directly review the obstacles facing the construction of the cooperative building, which has only reached 70.22% progress, despite being scheduled for full completion.

During the inspection, Dudung engaged in direct dialogue with the Chairperson of the Merah Putih Village Cooperative in Cipenjo, Mega, and the management team.

It was revealed that the construction project, which was targeted for completion within three months (last February), has been halted from March until the present. The construction stopped due to an internal leadership transition process within the local Military District Command (Kodim), as well as difficulties regarding the costs of land infilling.

Responding to these project obstacles, Dudung emphasised that he will immediately coordinate with the Kodim authorities to ensure that this village economic infrastructure development can proceed without further delay.

“So, this has been hindered because there was a change in leadership at the Kodim, causing the construction not to continue. The target was supposed to be only three months, right? I will inform the District Military Commander (Dandim) so that this can be completed promptly,” said Dudung.

Meanwhile, Mega also explained that there were additional technical challenges on the ground. “Yes. Previously, we were also hindered by infilling issues. This infilling matter has been a point of contention. From our side, we are preparing the land, but since infilling requires significant costs—we need approximately 30-40 dump trucks for the infill—this cost is being debated between the contractor and us, the cooperative,” she explained.

More from 26 June 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/construction-of-merah-putih-village-cooperative-in-cipenjo-stalls-dudung-there-was-a-changeover-at-the-kodim-1782460365)
Originally published by Republika (https://news.republika.co.id/berita/th88gt377/pembangunan-kopdes-merah-putih-di-cipenjo-mandek-dudung-ada-pergantian-di-kodim), translated from Indonesian
Print