Construction of Bekasi’s Bulak Kapal Flyover Targeted to Begin in November 2026
BEKASI — The Bekasi City Government in West Java is seeking to bring forward the contract signing for the Bulak Kapal flyover, aiming to hold it in mid-November 2026 by accelerating the acquisition of affected land plots.
“All land acquisition is targeted for completion by early November to meet the schedule for signing the contract in the middle of next month,” Bekasi Mayor Tri Adhianto Tjahyono said on Friday (30 October 2026), while accompanying Coordinating Minister for Infrastructure and Regional Development Agus Harimurti Yudhoyono (AHY) on a visit to the construction site in Bekasi.
Tri said efforts to accelerate the Rp188 billion infrastructure project, which has received direct attention from President Prabowo Subianto, were intended to ensure smoother traffic and improve road safety. Of the 76 land plots affected by the Bulak Kapal flyover project, 40 have been acquired, while the remaining 36 are expected to be settled soon.
The Bekasi City Government is focusing on expediting the acquisition of the remaining 36 plots, including land belonging to Perum Jasa Tirta (PJT), the Ministry of Social Affairs, and areas designated for social and public facilities.
“I have also conveyed the matter and asked the Coordinating Minister for Infrastructure and Regional Development, Mr AHY, to help with communication so that the government-to-government administrative process does not delay implementation,” he said.
Tri also said he was ready to take full responsibility for decisions on the use of land, including plots facing ownership issues. He set early next week as the deadline for resolving the remaining land acquisition.
The Bekasi City Government will use a consignment mechanism, depositing compensation payments with the court, to prevent disruption to work on site.
“The construction contract is scheduled to be signed on 14 November. Physical work on site is therefore projected to begin on 15 November,” he said.
He has instructed the relevant departments to give affected residents who have received land acquisition payments one week to demolish their buildings themselves. If they miss the deadline, officials will assist with the demolition.
The city has prepared a traffic-management plan to mitigate congestion during construction, making greater use of alternative routes along Jalan Ampera and Jalan Moh. Yamin, which are currently open and running smoothly.
The local government is also discussing with state railway operator PT Kereta Api Indonesia (KAI) the use of frontage land along the railway. The plan is for the Bulak Kapal area to be directly connected to Jalan Ampera and Jalan Moh. Yamin via a parallel road.
The measure is expected to make it easier for residents to travel without crossing the railway tracks and to support local economic growth. Once the project is complete, two level crossings, including the one on Jalan Ampera, are planned to be closed permanently for public safety.
“We have carefully prepared on-site mitigation, involving the Transportation Agency for traffic routes, the Housing, Settlement and Land Agency for land, and the Public Works and Spatial Planning Agency for infrastructure readiness. Everyone is working together. For us, the most important thing is not the groundbreaking ceremony, but when the final stone is laid,” he said.