Construction Cost of MRT Jakarta Bundaran HI-Kota Route Reaches Rp 25.3 Trillion
PT MRT Jakarta (Perseroda) has announced that the construction cost for Phase 2A of the North-South Line is Rp 25.3 trillion. The funding is sourced from a loan cooperation agreement between the Government of Indonesia and Japan.
Phase 2A of the North-South Line will connect Bundaran HI Station to Kota Station, spanning approximately 5.8 kilometres. The route consists of seven underground stations: Thamrin, Monas, Harmoni, Sawah Besar, Mangga Besar, Glodok, and Kota.
This phase is divided into two segments. Segment one, from Bundaran HI to Harmoni, is targeted for completion by the end of 2027, while segment two, from Harmoni to Kota, is targeted for completion by the end of 2029. The development progress of Phase 2A continues to show significant advancement.
As of 25 July 2026, overall construction had reached 62.68 percent, surpassing the target of 61.92 percent. For contract package CP201, construction progress reached 93.90 percent against a target of 93.89 percent. At Thamrin Station, the construction team has entered the work phase, including the reinstatement of pedestrian areas around the station site, the reconstruction of the Transjakarta Bus Rapid Transit shelter, mechanical, electrical, and plumbing (MEP) installation, and roofing and finishing works for entrances 5, 7, and 8.
Source: jawawa.id (https://jawawa.id/newsitem/construction-cost-of-mrt-jakarta-bundaran-hi-kota-route-reaches-rp-25-3-trillion-1786672347)
Originally published by Republika (https://news.republika.co.id/berita/tjqhns484/biaya-pembangunan-mrt-jakarta-rute-bundaran-hikota-rp-253-triliun), translated from Indonesian