Clarity Still Elusive on Plans to Add More Commuter Trains

| | Source: Republika Translated from Indonesian | Infrastructure
Clarity Still Elusive on Plans to Add More Commuter Trains
Image: Republika

The government is refining plans to expand the electric commuter train (KRL) fleet through several options, ranging from new trains produced by state-owned PT INKA and imported new trains to second-hand trains from Japan. Transport Minister Dudy Purwagandhi said he had discussed the matter with Danantara Indonesia and the State-Owned Enterprises Agency (BP BUMN), as well as the Industry and Trade Ministries.

“We understand the public’s need for more trains. We understand that people hope this need can be met quickly,” Dudy told reporters at the Transport Ministry’s media room on Jalan Medan Merdeka Barat in Jakarta on Friday (9 October 2026).

Dudy said the Transport Ministry supported state-owned railway operator PT Kereta Api Indonesia (KAI) in adding to the Greater Jakarta commuter-train fleet to meet strong public demand. KAI has funding through state capital injections (PMN) to procure additional trains, he said.

KAI received PMN funding in 2023 to procure 35 trainsets for Greater Jakarta and retrofit two existing trainsets by 2027. As of October 2026, KAI had brought in 11 new trainsets from China, all of which are in service, Dudy said.

“INKA is working on 16 trainsets. Seven [trainsets that had encountered problems] have returned to service; two are planned to be completed this year, and a further seven in 2027,” Dudy said.

This means procurement of 27 trainsets is targeted for completion by 2027. Dudy called on KAI to ensure INKA is ready to meet next year’s production target of seven trainsets.

“There is hope that this can be fulfilled as soon as possible. INKA’s production takes time; its average output is three trainsets a year,” he said.

Dudy said the 27 trainsets did not meet the target of 35 set out in the state budget, leaving a shortfall of eight. The Transport Ministry has asked KAI to complete procurement of all 35 trainsets in line with the state funding already allocated, he said.

“We are urging KAI to make up the shortfall by first completing the 35 trainsets approved in 2023. We also have to ensure they are fit for service and meet safety standards,” Dudy said.

KAI has received PMN funding totalling Rp9.53 trillion, allocated in stages: Rp2 trillion in the 2024 fiscal year, Rp1.8 trillion in 2025, and a planned Rp1.5 trillion in 2026. The funding is for 35 Greater Jakarta commuter-train trainsets and the retrofitting of two existing trainsets.

BP BUMN head and Danantara chief operating officer Dony Oskaria previously said Danantara was still assessing plans to import new or second-hand commuter trains. He said expanding the Greater Jakarta fleet was part of Danantara’s commitment to accelerating public transport development.

“We need to look at the costs and benefits, what the returns are and what we would get from it. We will discuss it with the Transport Minister,” Dony said after attending the sixth Executive Breakfast Meeting, titled “Two Years of Danantara”, hosted by IKA Fikom Unpad at The Tribrata Dharmawangsa in Jakarta on Friday (2 October 2026).

Dony said plans to import second-hand trains from Japan did not mean local production by INKA was being disregarded. INKA currently has limited production capacity and is undergoing a transformation process, he said.

More from 10 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/clarity-still-elusive-on-plans-to-add-more-commuter-trains-1791615057)
Originally published by Republika (https://ekonomi.republika.co.id/berita/tmofvq370/penantian-penambahan-krl-masih-menanti-titik-terang), translated from Indonesian
Print