Cirebon-Semarang II Gas Pipeline Stretching 242 Km Officially Operational
PT Perusahaan Gas Negara Tbk (PGN), acting as Pertamina’s Gas Subholding, alongside its subsidiary PT Pertamina Gas (Pertagas), has officially conducted the Commissioning Metering System for the Cirebon-Semarang II (CISEM II) natural gas transmission pipeline.
The 242-kilometre Cisem II pipeline connects to the already operational Cisem I pipeline, which runs from Semarang to Batang. The primary commissioning stage of Cisem II in Kandang Haur was successfully executed on Friday (5/6/2026).
All stages of facility testing and flow tests have been completed to ensure optimal system performance as part of the verification process for the full operational readiness of Cisem II, ensuring its integration with Pertagas’ existing operational facilities.
The Director General of Oil and Gas at the Ministry of Energy and Mineral Resources (ESDM), Laode Sulaeman, stated that the commissioning of Cisem II represents a significant achievement in national energy infrastructure development.
“Following the success of Cisem I, today we witness the commissioning of Cisem II, which completes the connectivity of the natural gas pipeline network on Java Island. This infrastructure strengthens national energy resilience and enhances the system’s capability to distribute gas to various regions and user sectors. We appreciate all parties who have collaborated so that this strategic project could be completed and operated effectively,” said Laode in a press release received on Tuesday (9/6/2026).
PGN Commercial Director Aldiansyah Idham noted that the successful commissioning of Cisem II demonstrates the PGN Group’s commitment to maintaining the sustainability of the national natural gas business through infrastructure strengthening and the optimisation of domestic energy utilisation. This success is the result of synergy among all stakeholders in supporting the optimal use of domestic natural gas.
“The Commissioning Metering System in East Kandang Haur is a vital step towards the full optimisation of the CISEM II infrastructure, providing greater flexibility and reliability for the national natural gas transmission system,” said Aldiansyah.
President Director of Pertamina Gas, Indra P. Sembiring, confirmed the full operational readiness of the Cisem II system. “With the completion of commissioning in East Kandang Haur, the Cisem II system is ready for operation and becomes a vital part of the national natural gas transmission network, which now connects East Java to West Java. Pertagas has prepared the facilities, infrastructure, and personnel spread from East Java to West Java to ensure the operation of this infrastructure runs safely, reliably, and optimally,” said Indra.