Chevron Pacific Indonesia has reiterated that its top officials were not guilty of wrongdoing in a site cleanup project, following the conviction on Thursday of a fourth official in a case whose validity has also been questioned by the government.

A. Hamid Batubara, the CPI president director, said on Friday that testimony from government officials and expert witnesses presented at the trial of Bachtiar Abdul Fatah, the general manager of CPI’s Sumatra operations, clearly proved that was not in violation of any laws with regard to a bioremediation project to clean up the soil at a former operation site in Riau.

Hamid said the Jakarta Anti-Corruption Court, which on Thursday ruled that Bachtiar was guilty and sentenced him to two years in prison, ignored the evidence, including certified test results, procedural documents, and testimony from credible expert witnesses.

He added that government officials had testified that CPI’s bioremediation program had the requisite permit and operated according to regulations.

Hamid also noted that the South Jakarta District Court had previously exonerated Bachtiar of all the charges in the case, and that he should never have been taken to the anti-corruption court.

CPI’s managing director, Chuck Taylor, said the company would continue supporting Bachtiar, although it respected the Indonesian judicial process.

CPI was required to conduct a bioremediation project at its oil fields in Duri, Riau. It appointed Green Planet Indonesia and Sumigita Jaya for the task, but the Attorney General’s Office alleges they were not qualified for the job.

Oil and gas regulator BPMigas was to refund CPI for the bioremediation costs. The AGO alleged that the project was never completed but that CPI claimed it was and collected the funds anyway — an allegation that both CPI and BPMigas, since restructured as SKKMigas, have continuously denied.

CPI said it paid for the cleanup itself and never sought reimbursement, while SKKMigas agreed that no money was handed over to CPI from the state.

However, despite the protestations and an order by the South Jakarta District Court to drop the case, the AGO has persisted, taking several officials to the Jakarta Anti-Corruption Court.

Ricksy Prematury, the president director of Green Planet, was convicted in May of corruption and sentenced to five years in prison, while Sumigita head Herland bin Ompo was sentenced in the same month to six years in prison.

Sumigita was ordered to pay a $6.9 million fine, while Green Planet was ordered to pay $3.1 million.

In July, Kukuh Kertasafari, the head of CPI’s environmental cleanup department, was sentenced to two years in prison.

Days earlier, Endah Rumbiyanti, an environmental manager at CPI, was sentenced to two years in prison.

The rulings came a month after Widodo, another CPI employee, was given a seven-year sentence.

Sumigita’s Herland has since had his sentenced slashed to three years upon appeal. The others have also mounted appeals against the rulings against them.

Bachtiar’s lawyer, Maqdir Ismail, previously said that Bachtiar had never abused his power and instead he was asked by CPI’s president director to sign the contract for the cleanup, and that BPMigas even approved the value of the tender.

He said a supervisor from the Environment Ministry was charged with monitoring and supervising the bioremediation projects, and that the ministry had maintained that CPI had not been found to be in breach of the law.

Maqdir said there was no state loss from the project because the government had already offset $9.86 million from the obligations of BPMigas for the underwriting of CPI, and that the amount offset covered the costs for the bioremediation activities.

He also took the prosecutors to task for mistakenly alleging that the state lost $220,000 as a direct result of Bachtiar’s role in the bioremediation project.

The amount was later changed to $228,000 at the prosecutor’s recommendation to the panel of judges, Maqdir said, arguing that such a change should not have happened after the trial had begun.

More from 19 October 2013 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/chevron-defends-executive-convicted-in-case-built-on-shaky-foundation-1382115600)
Originally published by The Jakarta Globe (http://img.thejakartaglobe.com/2013/10/IMAL5624_preview-1024x730.jpg)
Print