Change Again! Sleman Regency Government Confirms Relocation of SDN Nglarang
The Sleman Regency Government (Pemkab Sleman) has once again changed its policy regarding the relocation of SD Negeri Nglarang, which is impacted by the Jogja-Solo toll road project. After previously cancelling the relocation, Pemkab now states that the school will be relocated to a new location.
Assistant for Government and Public Welfare at the Sleman Regional Secretariat, Agung Armawanta, explained that this relocation decision is now final. He stated that replacement land has also been prepared. The location is north of the toll road project site and remains within the same sub-district.
“So this is hopefully final. The land for SDN Nglarang will take the site to the north, which was previously the third alternative land,” said Agung to reporters at the Sleman Regency Secretariat pendopo on Monday (6/4/2026).
He explained that one reason for the delay in relocation was issues with replacement land that had the status of Sustainable Food Agricultural Land (LP2B) or Protected Wetland (LSD). This eventually led to the option of cancelling the relocation.
However, in the latest meeting, it was decided to proceed with relocating the school. Meanwhile, for the replacement land, it was agreed to use village-owned land (TKD) in the form of dry fields.
“So yes, considering many aspects. First, the land regulations. Then, this is acceptable to the community. Access to the environment is still easy,” he said.
The prepared replacement land measures 4,812 square metres, with a budget received from PT Jasamarga amounting to Rp 3.1 billion. Agung explained that during the construction process, Pemkab will still prepare additional funding according to the site plan.
“Later, the Regent’s policy on the amount (additional budget). This April, the site plan adjustment process,” he clarified.
While waiting for construction to proceed, the teaching and learning process for students will continue in the old building.
“Hopefully completed this year, but for the temporary learning location, it’s at the current site,” he said.
Three Classrooms to be Demolished
Meanwhile, the Public Relations of PT Adhi Karya Tol Jogja-Solo Package 2.2, Agung Murhandjanto, explained that in a meeting with local government and related parties, it was agreed to carry out initial demolition. He stated that three classrooms to be demolished include classes 4, 5, and 6.
“From Adhi Karya’s side as the contractor, our commitment is that demolition starts after 24 April until 5 May because there are exams,” said Agung when contacted by reporters.
He said that according to the agreement, after the three classes are demolished, the teaching and learning process for students will be moved to the hall. During the construction process, the contractor will prepare several supporting facilities such as toilets for students.
“Then, for teaching and learning activities, move to the hall. That’s already prepared by the school side. Our task is to prepare toilets and utilities during the relocation process,” he said.
Agung continued that the three classrooms are right at the foot of the embankment. Therefore, after being demolished, the contractor will build a boundary fence to ensure project safety. Meanwhile, regarding the construction plans, Agung said that is under PT Jasamarga’s authority.
“The implementation of construction is from Jasamarga, the funds are there. From the contractor, the task is to demolish the affected classes and then tidy up the work area with safety fences,” he concluded.
Previously reported, Sleman Regent Harda Kiswaya revealed the cancellation of SDN Nglarang’s relocation for several reasons. Harda explained the reasons for cancelling the relocation after communicating with the sub-district head and related agencies regarding the replacement land that had not been obtained. Meanwhile, students need certainty soon to learn comfortably.
“I ask the sub-district friends to understand. Alhamdulillah, it’s already possible. So we’ve agreed that the SD (Negeri Nglarang) won’t move,” said Harda when contacted by reporters on Thursday (12/3).
At that time, the budget was also a consideration. The allocated budget was limited to Rp 3.1 billion. He said the provided budget was not sufficient to reach the building construction stage.
“This (reason not to move) is from the existing conditions. The replacement land is complicated, and the money is Rp 3.1 billion. That means for land and building, it’s not enough,” he said at the time.
Source: jawawa.id (https://jawawa.id/newsitem/change-again-sleman-regency-government-confirms-relocation-of-sdn-nglarang-1775623939)
Originally published by detikJogja (https://www.detik.com/jogja/berita/d-8431855/berubah-lagi-kini-pemkab-sleman-pastikan-relokasi-sdn-nglarang), translated from Indonesian