Buleleng Regional Council Inspects Drainage and Diponegoro Street Improvement Project, 27% Complete
Image: detikBali

Physical progress on the drainage construction and improvement of Diponegoro Street, around Pasar Anyar in Singaraja, Buleleng, Bali, has reached only 27%. The finding came after members of Commissions II and III of the Buleleng Regional House of Representatives (DPRD) monitored the project on Monday (12 October 2026).

The council highlighted several on-site obstacles that could hinder the Rp4.74 billion project. These included vehicle parking, traders operating near the site and technical conditions affecting the old drainage channel.

Wayan Masdana, chairman of Commission II, said the issues needed to be promptly coordinated with the relevant local government agencies to prevent delays.

“We want to ensure that this project is progressing properly. Our inspection found several outstanding issues, involving parking, traders and the technical condition of the drainage channel, which need to be coordinated with the relevant agencies so they do not delay completion,” Masdana said.

The project is being carried out by CV Cadudasa Pratama, with supervision by CV Manca Geni, under a contract worth Rp4,749,733,000. The work is scheduled to take 120 calendar days, running from 28 August to 17 December 2026.

Masdana urged the contractor, supervising consultant and local agencies to strengthen coordination so the project could be completed on time. He said the on-site issues should be assessed promptly to keep work on schedule without compromising quality. The project is expected to be completed in accordance with the contract and benefit traders, road users and people living around Pasar Anyar Singaraja.

As well as improving the Pasar Anyar area, the drainage works are expected to improve water flow and reduce the risk of standing water and flooding. The Buleleng council stressed that the project should not focus solely on meeting its deadline, but should also ensure the drainage system functions effectively.

More from 12 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/buleleng-regional-council-inspects-drainage-and-diponegoro-street-improvement-project-27-complete-1791802230)
Originally published by detikBali (https://www.detik.com/bali/berita/d-8703677/dprd-buleleng-cek-proyek-drainase-penataan-jalan-diponegoro-progres-27), translated from Indonesian
Print