Broken EHV Transmission Line Suspected as Cause of Sumatra Blackout
JAKARTA, KOMPAS.com - The Indonesian National Police’s Criminal Investigation Agency (Bareskrim) has uncovered a broken extra high voltage (EHV) overhead transmission line suspected of causing a widespread blackout across parts of Sumatra on Friday, 22 May 2026.
The damaged cable was displayed at Bareskrim’s headquarters during a press conference on Monday, 25 May 2026.
“The broken transmission cable was found near a transmission tower in Temino Village, Mestong Subdistrict, Muaro Jambi Regency, Jambi Province,” said Bareskrim Deputy Chief Inspector General Nunung Syaifuddin during Monday’s press conference.
The cable was discovered during a joint investigation by Bareskrim and PT PLN at the transmission tower site in Temino Village, Mestong Subdistrict, Muaro Jambi Regency, Jambi Province, on Sunday, 24 May 2026.
Despite the broken cable, the transmission tower itself was reported to be in good condition with no significant damage.
According to Nunung, initial investigations indicated the transmission network disruption occurred on Friday at around 6:44 pm Western Indonesian Time (WIB).
The disruption is suspected to have been triggered by severe weather causing the transmission system to disconnect from Sumatra’s power grid interconnection.
Initial field reports suggest the transmission cable snapped suddenly due to extreme weather conditions.
This suspicion was reinforced by local residents’ testimonies of hearing an explosion shortly before the power outage.
“An explosion occurred just before the power outage in the transmission tower area,” Nunung said.
Bareskrim also confirmed no evidence of sabotage or intentional involvement in the blackout incident so far.
“The damage or break in the cable or network is not clean. It appears frayed. If it were sabotage, the cuts would be neater,” Nunung said.
He added that preliminary causes point to technical issues and extreme weather, such as mechanical friction from wind, loose connections causing heat, or cable movement due to severe weather.
Currently, Nunung said, the power system across Sumatra has been restored to normal and is operating safely and stably, according to PT PLN’s official statement.
Source: jawawa.id (https://jawawa.id/newsitem/broken-ehv-transmission-line-suspected-as-cause-of-sumatra-blackout-1780161320)
Originally published by Kompas (https://nasional.kompas.com/read/2026/05/25/13021241/ini-penampakan-kabel-sutet-diduga-pemicu-blackout-di-sumatera?utm_source=ABC&utm_medium=rss), translated from Indonesian