The Gunungkidul BPBD has prepared personnel along the Clongop New Road in Gedangsari, Gunungkidul, to anticipate potential follow-up landslides. This measure is taken because the embankment conditions at the site remain unstable and prone to landslides during rain.

Several landslides have been recorded along that route during heavy rain. The most recent landslide occurred on Thursday (16 April) and resulted in the route being managed with an open-closed system.

The Head of Operations for Gunungkidul BPBD, Purwono, stated that officers have been placed at the location to monitor conditions and carry out rapid handling if a landslide occurs.

“Because the hill is indeed still unstable, we are on standby. We have stationed personnel there, always coordinating with local government and police,” said Purwono when contacted by reporters on Sunday (19 April 2026).

Although prone to risks, the Clongop route is currently passable by vehicles. However, road users are urged to remain vigilant as conditions can change at any time.

“For now, it is still passable, but conditionally,” he said.

He explained that landslides along that route are generally triggered by rain. Therefore, monitoring is intensified, especially during high rainfall.

“Usually triggered by rain. When it rains, we check the location, and if a landslide occurs that blocks the road, we close it,” he stated.

Purwono mentioned that handling is carried out using an open-closed road system. Landslide materials blocking the road will be promptly removed before access is reopened.

“If there is a landslide, we clear it first, then reopen it. So far, the approach has been open-closed,” he clarified.

Furthermore, Purwono said the route is a provincial road and has been coordinated with the Provincial Public Works Department (PU) for further handling.

“We have written to the Provincial PU. It is planned to be included in the amended budget handling,” he revealed.

For a long-term solution, embankment handling is planned using gabion wire, considering the soil condition dominated by clay.

“Possibly with gabion wire, but this is still under study by PU,” he said.

He added that the height of the embankment at the landslide site reaches about 25 metres. This condition makes the potential for follow-up landslides still quite high.

“The embankment height is around 25 metres. So we must be careful because there is potential for follow-up landslides,” he concluded.

Previously reported, heavy rain that hit the Gedangsari Sub-District caused a landslide on the Clongop New Road, Gedangsari, Gunungkidul. As a result, most of that route was covered with landslide materials and had to implement an open-closed road system.

The Head of Emergency and Logistics Division of Gunungkidul BPBD, Edy Winarta, said the incident began when rain of moderate intensity hit Watugajah, Gedangsari, on Thursday (16 April 2026) around 11:00 p.m. WIB. Then, the next morning at 06:20 a.m. WIB, residents found landslide materials on the Clongop New Road.

“After checking, it turned out there was a landslide on the Clongop New Road,” he said when contacted by reporters on Friday (17 April 2026).

This was followed by reports from residents to the Gunungkidul Regency BPBD. Upon receiving the report, BPBD officers immediately went to the incident site to conduct an assessment.

“The assessment result showed that the landslide materials covered 70% of the Clongop New Road’s surface,” he stated.

As for casualties or injuries, Edy said there were none. This was because during the heavy rain, officers immediately closed the route to the Clongop New Road.

However, the landslide disrupted road access from Gedangsari to Klaten. Even now, officers are still cleaning the landslide materials.

“For motor vehicles, they can still pass, but an open-closed system is enforced because the landslide materials are not fully cleaned,” he said.

Before that, landslides occurred several times, such as on 3 March, 17 March, 27 March, and 2 April.

More from 19 April 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/bpbd-stations-personnel-along-clongop-route-following-repeated-landslides-during-rain-1776585047)
Originally published by detikJogja (https://www.detik.com/jogja/berita/d-8451266/bpbd-tempatkan-personel-di-jalur-clongop-usai-longsor-berulang-saat-hujan), translated from Indonesian
Print