Bogor Regency Government begins repairs to Bojonggede Skybridge escalators
Bogor, West Java (ANTARA) — The Bogor Regency Government in West Java has begun repairing three escalators at the Bojonggede Skybridge, which have been out of service for the past four months because of damage to several components.
Bogor Regency Transportation Agency head Bayu Ramawanto said in Bojonggede on Wednesday that repairs are expected to be completed by mid-December 2026, allowing the facility linking the area to Bojonggede Station to be used by the public again.
“On behalf of the Bogor Regency Government, we offer our deepest apologies for the inconvenience caused to users, particularly those who have been unable to use the Bojonggede Skybridge escalators for around four months,” Bayu said.
Repairs are important because Bojonggede Station is one of the busiest stations in the Bogor area, serving around 50,000 KRL commuter train passengers a day.
The Bojonggede Skybridge connects the commuter train station with Bojonggede Terminal, making it easier for people to transfer between modes of transport.
Bayu explained that the escalators were taken out of service to prevent accidents caused by damaged components that could endanger users. He said the local government did not want to operate them until all components had been confirmed safe and functioning normally.
The Bogor Regency Government has allocated around Rp800 million through the 2026 revised regional budget to repair several facilities at the Bojonggede Skybridge. Around Rp400 million of that amount is earmarked for the three escalators, with the remainder for repairs to the stairs, roof, bridge joints and lighting.
Bayu acknowledged that the previously available maintenance budget was insufficient to address all the damage, prompting the local government to seek additional funding.
“This year we had already made arrangements using the maintenance budget from the regional budget, but after calculating the costs, it turned out to be insufficient. We therefore sought an increase through the revised budget,” he said.
He confirmed that repair work would begin this week, with technicians addressing the damaged components.
Meanwhile, senior Skybridge repair technician Gatot Digdiya Sulaksono said dismantling of the escalators began on Wednesday afternoon to assess the damage and replace components that were already available.
An initial inspection found damage to the motor bearings, escalator handrails and several other drive components, he said. The damage could put users at risk if the escalators continued operating, particularly under a heavy passenger load.
“If we run it, the bearings are already faulty. The motor’s rotation could be disrupted, and we are concerned the escalator could slip under peak loads,” Gatot said.
He added that some parts of the escalators were also broken, potentially trapping users’ feet.
Repairs to each escalator are expected to take more than a week, depending on the extent of the damage and the availability of spare parts, some of which still need to be ordered.
“Our target is to complete the work by mid-December,” he said.
Gatot added that all escalators must undergo inspections and safety tests before returning to service. Regular maintenance will also be needed to prevent similar damage and ensure the continued operation of the public facility.