Bogor Line Serves 78.08 Million Passengers in First Half of 2026, Becomes Busiest KRL Route
PT Kereta Api Indonesia (Persero) has recorded the Bogor Line as the KRL Commuter Line route with the highest passenger volume. Throughout January to June 2026, the Bogor Line served 78,077,679 passengers, underscoring the significant dependence of communities in Bogor, Depok, and surrounding buffer zones on rail-based public transport.
The role of the Bogor Line has continued to strengthen in recent years. In 2022, the route served 102,054,022 passengers. This figure rose to 133,040,885 passengers in 2023, then to 145,920,264 passengers in 2024, and reached 155,009,997 passengers in 2025.
KAI Vice President Corporate Communication Anne Purba stated that the high passenger volume on the Bogor Line demonstrates that the KRL has become an essential part of daily travel for the public, particularly for work commutes, education, economic activities, and connectivity to Jakarta.
“The Bogor Line is one of the main routes supporting daily public mobility. With 78.08 million passengers in the first half of 2026, strengthening service capacity is a crucial requirement so that public journeys can continue to be more orderly, comfortable, and reliable,” said Anne.
Within the route, Bogor Station is the node with the highest passenger activity. Throughout January to June 2026, Bogor Station recorded 18,451,462 KRL passenger movements, comprising 9,371,057 gate-ins and 9,080,405 gate-outs. The average passenger movement at Bogor Station reached approximately 101,942 per day.
In the list of the five stations with the highest KRL passenger movements in the first half of 2026, Bogor Station ranked first with 18,451,462 passenger movements. The next positions were occupied by Tanah Abang Station with 17,291,480 passenger movements, Sudirman Station with 13,078,339 passenger movements, Citayam Station with 11,465,614 passenger movements, and Bekasi Station with 11,425,878 passenger movements.
Anne explained that this data forms the basis for KAI’s preparations to increase service capacity on the Bogor Line. One such effort involves the development of platforms for tracks 6, 7, and 8 at Bogor Station to support the operation of 12-carriage KRL Commuter Line trains, known as SF12.
“The readiness of SF12 is part of the effort to enlarge capacity in a single journey. For passengers, the benefits can be felt through more adequate space, a more orderly boarding and alighting flow, and better travel readiness, especially during peak hours,” said Anne.
Currently, the platform development work for tracks 6, 7, and 8 at Bogor Station has entered the finishing stage and is running parallel with operational trials. The work, which began on 15 April 2026, is targeted for full completion on 15 July 2026.
The development includes preparatory work, structural and architectural works, mechanical, electrical, and plumbing (MEP), railway track works, and overhead catenary system (LAA). KAI has also installed overcapping or canopies on the platforms to improve passenger comfort while waiting for the KRL, both in hot and rainy weather.
As part of the work completion, KAI conducted a load test using a locomotive on 29 June 2026, followed by a KRL operational trial on 1 July 2026. These stages are carried out to ensure safety readiness, infrastructure reliability, and operational smoothness before the facilities are used optimally.
KAI, together with KAI Commuter, continues to coordinate so that passenger services remain safe, orderly, and smooth during the construction process. Passenger flow arrangements, service information, and instructions from station officers are prepared to maintain public mobility.
In addition to strengthening capacity at Bogor Station, KAI and the Directorate General of Railways at the Ministry of Transportation are also continuing to prepare connectivity between Bogor Station and Bogor Paledang Station. This integration is important to facilitate passenger transfers from the Commuter Line to the KA Pangrango service and other transport modes in the Bogor area.
“KAI wants to ensure that service improvements are made according to passenger needs. The Bogor Line serves millions of daily public journeys each year, so capacity readiness, safety, and connectivity are the main concerns in service development,” Anne concluded.
Source: jawawa.id (https://jawawa.id/newsitem/bogor-line-serves-78-08-million-passengers-in-first-half-of-2026-becomes-busiest-krl-route-1783418246)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5638881/7808-juta-pelanggan-semester-i-2026-bogor-line-jadi-lintas-krl-dengan-mobilitas-terbesar), translated from Indonesian