Blora Regency Government and Council Push to Accelerate Sekolah Rakyat
Blora (ANTARA) – The Blora Regency Government and local council leaders are stepping up coordination with the Ministry of Social Affairs and the Ministry of Public Works to accelerate construction of a Sekolah Rakyat in Cepu district.
“The move is intended to ensure the site is ready and speed up the stages of construction of the education facility,” Blora Regent Arief Rohman said in Blora, Central Java, on Tuesday.
The regent travelled to Jakarta on Monday (19 October) with Deputy Regent Sri Setyorini, Blora Regional House of Representatives Speaker Mustopa, Deputy Speaker Lanova Chandra and officials from regional government agencies for coordination visits to the two ministries.
At the Ministry of Social Affairs, the delegation was received by Secretary-General Muhamad Hasan Chabibie and officials. At the Ministry of Public Works, they met Aris Rudianto Nugroho, Acting Director of Systems and Strategy for Strategic Infrastructure Provision at the Directorate General of Strategic Infrastructure.
Arief said the central government supported accelerating construction of the Sekolah Rakyat in Blora. The regency hopes inter-ministerial coordination will expedite the site designation, an important step towards beginning construction.
“The ministries support accelerating construction of the Sekolah Rakyat. Blora is ready to operate one. We are now waiting for the site designation from the Ministry of Public Works and the Ministry of Social Affairs,” he said.
He said the regional government would continue coordinating with the central government, particularly on completing requirements and designating the construction site.
During the meeting with Ministry of Public Works officials, Arief presented the regency’s preparations for the Sekolah Rakyat site in Cepu district. He said the site had been inspected by the relevant work unit, including checks on road access to the development area.
“Following the work unit’s survey, the land has been inspected and prepared. The access road is also eight metres wide. Filling and limestone work is under way,” he said.
According to the weekly report on land-filling work for 12–18 October 2026, physical progress had reached 95.70 per cent. This was above the planned target of 85.81 per cent, putting the work 9.89 percentage points ahead of schedule.
The regional government has built a 323-metre-long concrete access road, eight metres wide. It has also prepared basic infrastructure, including a clean-water connection through the regional water utility (PDAM) and a three-phase electricity connection from state-owned electricity company PLN.
Arief said the next stages would be coordinated with the Ministry of Public Works’ work unit. He added that a follow-up by the relevant work unit on site readiness was planned for 27 October 2026.
In its presentation to the ministries, the Blora Regency Government also requested central government support to complete earthworks on the remaining land, covering about 2.9 hectares, and to carry out soil and topographical investigations and prepare the technical design for construction.
Accelerating the Sekolah Rakyat project requires coordination between regional and central government, particularly to complete technical and administrative requirements and designate the site. The Blora Regency Government said it was ready to continue coordination so the construction stages could proceed as planned.
Through these efforts, the regional government hopes construction of the Sekolah Rakyat in Cepu district will soon move to its next stage. The programme is part of an effort to widen access to education, and the facility is expected to provide educational infrastructure needed by the people of Blora.
Source: jawawa.id (https://jawawa.id/newsitem/blora-regency-government-and-council-push-to-accelerate-sekolah-rakyat-1792515088)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5800625/pemkab-dprd-blora-perjuangkan-percepatan-sekolah-rakyat), translated from Indonesian