Batang Power Plant Project Faces More Delays
The Jakarta Globe By Tito Summa Siahaan
Jakarta. The nation’s first and largest public-private partnership project, the 2,000 megawatt Batang coal-fired power plant in Central Java, faced another delay, prompting its operator, Bhimasena Power Indonesia, to declare force majeure on Tuesday, according to a statement from Adaro Power.
Adaro Power, the country’s second-largest coal miner, owns a 34 percent stake in Bhimasena Power Indonesia (BPI).
It said the difficulties in acquiring land for the project remained the biggest hurdle.
J-Power and Itochu, both Japanese firms, own a 34 percent and a 32 percent interest in the consortium, respectively.
The statement said the consortium had acquired more than 85 percent of the land needed for the project as well as obtaining approval for its environmental impact assessment (Amdal) and other necessary permits.
The project will require an area of around 226 hectares.
“However, due to the instability of the situation at the site, the acquisition of the remaining plots of land are beyond the reasonable ability of a private company, like BPI, to acquire and may be acquired only with government support.”
“BPI came to the conclusion that the circumstances and events delaying the land acquisition process are not within BPI’s reasonable control,” it added.
Still, BPI is committed to continue the project, the statement assured.
According to the original plans, the Batang power plant, which was awarded to BPI in 2011, will begin construction in 2012 and was slated for commercial operation by the end of 2016.
Under the current condition, the power plant may commence commercial operation by 2019 at the earliest.
The project is estimated to cost some $4 billion, with around $2.7 billion that will be financed through loans from Sumitomo Mitsui Banking Corporation and Japan Bank for International Cooperation.
Jarman, the director general for electricity at the Ministry of Energy and Mineral Resources, said the government was aware of the condition and preparing a series of mitigation measures to anticipate a power deficit in densely populated Java.
The government estimated that the power plant, if completed, would supply around 30 percent of Java’s electricity requirements.
Jarman said that the government was planning to build several power plants with a combined capacity of 2,000 MW to plug the power deficit.
“The projects are the 800 MW Muara Karang gas-fired power plant and the 800 MW Tanjung Priok gas-fired power plant, both in North Jakarta, and the 400 MW Muara Tawar gas-fired power plant in West Java.”
In addition, the government planned to expand the Cirebon coal-fired power plant in West Java, doubling its generating capacity to 2,000 MW.
Nur Pamudji, president director of state utility firm, Perusahaan Listrik Negara, confirmed the plan, adding that all the alternative projects must commence operations by 2018.
“Currently, the projects are being set up and we will announce when ready,” Nur said.
Chairul Tanjung, the chief economic minister, said last month, that the local administrations were given one more opportunity to sort up the land acquisition issues before the central government intervenes using the 2011 Land Acquisition Law, which will come into full force next year.
Source: jawawa.id (https://jawawa.id/newsitem/batang-power-plant-project-faces-more-delays-1404838800)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/business/batang-power-plant-project-faces-delays/)