Batam Blackout: Bahlil and PLN Chief Explain the Cause
Jakarta, CNBC Indonesia – Energy and Mineral Resources Minister Bahlil Lahadalia has spoken about the cause of the total power outage in Batam and parts of Bintan and Tanjung Pinang, which began on Monday (12 October 2026) and continued into Tuesday (13 October 2026). Bahlil said the outage was triggered by technical problems with the electricity network.
He said PLN had reported network disruptions caused by lightning strikes as well as interference from wild animals.
“Yes, there were several technical problems in the Batam area. Some parts of the network were disrupted by lightning strikes and, according to them, there was a technical fault,” Bahlil said.
“There were three technical causes, one of which was an animal, such as a bat, coming into contact with the network,” he added.
Asked whether affected residents might receive compensation, Bahlil said he could not yet confirm this. He said the matter would need to be discussed with the management of state-owned electricity company PT PLN (Persero).
“I will discuss it first with PLN, because PLN is best placed to understand the technical implementation in the field,” Bahlil said.
Separately, Suroso Isnandar, PLN’s Director of Project Management and Renewable Energy, said the company was still investigating the precise cause of the total outage in the area.
“We are investigating it thoroughly. We are not ruling out various possible causes, and we will assess which areas need to be improved,” he said.
However, he said a fault in one transformer was generally the main trigger for the total blackout in Batam. PLN will therefore review maintenance across its facilities to support rising electricity demand, including in Batam.
Suroso added that electricity supplies in Batam had now been fully restored. Restoration in Bintan and surrounding areas was continuing in stages, with a full return to service expected soon.
PLN is still assessing whether compensation should be paid to affected residents.
“Under the applicable regulations, there is a compensation mechanism if an outage exceeds a certain number of hours. However, our main priority now is restoring services to the public,” Suroso said.
“We will review the matter once restoration is complete. Our focus at the moment remains on dealing with the effects of the outage that began yesterday,” he concluded.
Source: jawawa.id (https://jawawa.id/newsitem/batam-blackout-bahlil-and-pln-chief-explain-the-cause-1791985874)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20261014184430-4-776269/batam-blackout-bahlil-hingga-bos-pln-ungkap-penyebabnya), translated from Indonesian