Basuki Says He Did Not Order Halt to Elevated Road Project

| Source: The Jakarta Globe

The Jakarta Globe by Lenny Tristia Tambun

photo: Motorists use the Antasari-Blok M elevated road in South Jakarta for the first time in January. (JG/Safir Makki)

Jakarta Deputy Governor Basuki Tjahaja Purnama on Wednesday said that it was the cash-strapped contractor who decided to put an elevated road project in the capital on hold, not the city administration.

"What needs to be straightened is about the one who halted the project. It was not us who did it. No. It [the contractor] did it because it was not paid," Basuki said, referring to state-owned company Istaka Karya.

Basuki said the contractor "maybe ran out of money."

'But for us, we cannot pay if it [the project] is not audited first," he added.

Basuki on Monday said that the city administration had decided to put the nearly finished elevated road linking Kampung Melayu, East Jakarta, and Tanah Abang, Central Jakarta, on hold, amid suspicion it exceeded the city's budget.

“I just want to check to see if the project has any indication of default. Why was the project not completed on last year’s budget?” Basuki said at the time, adding that he would ask the Supreme Audit Agency (BPK) and the State Finance and Development Comptroller (BPKP) to audit the project. He added that if the BPK and BPKP did not find any violations, then the construction — which is 90 percent completed — would be continued.

“If the development was continued but it turned out [the project had] violated the regulations, who would take the responsibility? I pity the governor [Joko Widodo]. Therefore, the project needs to stop now [until we] see the audit result. If there is no problem with the audit then I promise I will let the project to proceed, either through re-opening the tender or other ways,” Basuki said on Monday.

Basuki said that Istaka was owed some Rp 20 billion ($2 million) for the work but the sum could not yet be paid after there were indication found of swelling work volume in the construction of the road.

"That is where the problem is. If the results of the audit shows that we should pay, we have the budget and we will pay," he said.

He said that some 17 percent of the physical work was yet to be done and added that the city administration was also ready to re-tender the remaining work if necessary.

Construction started in 2011 during then governor Fauzi Bowo’s tenure and was supposed to be completed by the end of 2012.

Another elevated roadway, which started construction at the same time, a 5-kilometer road that stretches from Antasari to Blok M in South Jakarta has already been complteted. Construction for the Kampung Melayu-Tanah Abang roadway and the Antasari project cost a total of Rp 2.2 trillion.

More from 24 April 2013 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/basuki-says-he-did-not-order-halt-to-elevated-road-project-1366736400)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/home/basuki-says-he-did-not-order-halt-to-elevated-road-project/587826)
Print