Bandung to Develop Railway Project

| Source: The Jakarta Post

The Jakarta Post By Arya Dipa

In an effort to solve the severe congestion in Bandung municipality, West Java, the central government has decided to assist the development of the Bandung Urban Railway Transportation project.

The government has received a loan from France of US$157 million for the project and the electrification of the 24-kilometer Padalarang-Gedebage line.

Director general of railways Tundjung Inderawan recently said that based on the agreement, the loan would be allocated for electrification, signaling and extending double track lines.

Tundjung said the project was in the final stages of documentation and tender. “If the tender is completed this year, the project could start operating by 2016,” he said.

According to the Medium Term Overseas Loans Planning List/2011-2014 Bappenas Blue Book, the urban railway project and the Padalarang-Cicalengka electrification require total funds of $175 million.

A 5-km stretch of the double tracks from Kiaracondong to Gedebage stations has been completed, including the signaling and telecommunication system for the overhead railway electrification system, including the construction of a 4.1-km elevated track in the center of Bandung city.

Residents have thus far been served by local diesel trains on the 42 kilometers from Padalarang to Cicalengka stations, 20 km of which is in the form of double track and uses an electronic signaling and relay signaling system, while the rest is single track with mechanical signaling.

State railway company Kereta Api’s (KA) Bandung Operational Zone 2 spokesman Jaka Jarkasih warmly welcomed the government’s plan.

KA Bandung Operational Zone 2, he said, had carried almost 5 million passengers on its air-conditioned diesel express, non air-conditioned diesel express and Bandung Raya economy trains in the first six months of this year.

The economy-class trains carried the most passengers, at more than 4.2 million. KA Bandung Operational Zone 2 daily operates 18 local economy-class trains, 10 air-conditioned express trains and 13 non air-conditioned express trains.

The local business and economy class trains operate on the Padalarang-Cicalengka line.

“Double tracks could increase the number of passengers, especially as traffic congestion gets worse [in Bandung],” added Jaka.

More from 5 August 2013 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/bandung-to-develop-railway-project-1375635600)
Originally published by The Jakarta Post (http://www.thejakartapost.com/news/2013/08/05/bandung-develop-railway-project.html)
Print