BALIKPAPAN – After inaugurating the receipt of gas from Jangkrik North East #6 (JNE#6) and the production facilities at the Maha-South Hub field offshore in East Kalimantan, Coordinating Minister for Downstreaming and Energy Transition Bahlil Lahadalia continued to the Balikpapan Refinery on Thursday (22 October 2026). He visited the Refinery Development Master Plan (RDMP) project, which is nearing completion and is intended to reduce fuel imports.
“The RDMP as a whole is 99% complete. It’s just the little finishing touches, as you’d expect with something new. New equipment has its rubber parts and things like that. But, God willing, we will get it done,” said Bahlil, who also serves as Minister of Energy and Mineral Resources.
The remaining work, Bahlil explained, involves technical adjustments and commissioning the new equipment so the refinery can operate at full capacity. While awaiting full operations, he said fuel supplies would remain secure.
Bahlil stressed that national fuel stocks were safe and met minimum standards. Pertalite stocks were sufficient for 16 to 18 days, while non-subsidised RON 92, 95 and 98 fuels were available for more than 20 days. Diesel supplies were also unobstructed, as national demand was being met without imports. In Kalimantan, fuel availability was broadly in line with the national average.
Alongside ensuring fuel availability, Bahlil called on Pertamina to optimise distribution so subsidised fuel reaches eligible members of the public. Monitoring of distribution is also being stepped up with local governments and law-enforcement authorities, including the military and police, particularly to crack down on stockpiling.
Distribution challenges remain in some areas. Bahlil said the El Niño phenomenon had caused the Kapuas River in West Kalimantan to become shallower, temporarily disrupting fuel deliveries. Pertamina responded by using ships as floating storage and then transporting fuel to its destination by road.
In the longer term, the Balikpapan RDMP is expected to play a major role. The National Strategic Project represents an investment of US$7.4 billion, or around Rp126 trillion, making it one of the largest investments by a state-owned enterprise at a single site.
Once fully operational, the refinery is expected to meet 22–25% of national fuel demand. This would strengthen supplies for the public and further reduce dependence on fuel imports, in line with President Prabowo Subianto’s Asta Cita agenda.
Accelerating operations
In Jakarta on Friday (23 October 2026), Bahlil urged the acceleration of full operations at Pertamina’s Balikpapan RDMP refinery in East Kalimantan.
“I have asked them to speed up repairs to anything that is still experiencing problems,” Bahlil said.
Bahlil said he had visited the Balikpapan Refinery on Thursday (22 October), after inaugurating the receipt of gas from Jangkrik North East #6 (JNE#6) and the production facilities at the Maha-South Hub field offshore in East Kalimantan.
Source: jawawa.id (https://jawawa.id/newsitem/bahlil-urges-faster-completion-of-balikpapan-refinery-set-to-supply-25-of-national-fuel-1792767090)
Originally published by Republika (https://ekonomi.republika.co.id/berita/tnd6ss483/tinjau-rdmp-balikpapan-bahlil-dorong-percepatan-kilang-ditargetkan-penuhi-25-persen-bbm-nasional), translated from Indonesian