Bahlil to Cut Tender Bureaucracy to Accelerate 100 GW Solar Power Project
Jakarta (ANTARA) - The Minister of Energy and Mineral Resources (ESDM), Bahlil Lahadalia, has stated that his department will cut bureaucracy to shorten the tender process, thereby accelerating the realisation of the 100 gigawatt (GW) solar power plant (PLTS) construction programme.
“Currently, I am adjusting regulations for companies that are truly competitive and possess excellent technological capabilities; we are considering that tenders do not need to take too long,” said Bahlil during the Electricity Connect 2026 event held in Tangerang, Banten, on Tuesday.
Bahlil stated that he will directly appoint companies that demonstrate economic value, rather than undergoing protracted tender processes, to shorten the implementation timeline of the 100 GW solar programme.
“We are cutting the bureaucracy. If it is economically viable, we will simply appoint them. There is no need for it to take too long; the important thing is that it is mutually beneficial and a win-win. A win-win outcome is what matters most,” said Bahlil.
In a separate instance, the Acting Director General of Electricity at the Ministry of ESDM, Tri Winarno, explained that this bureaucratic reduction involves shortening lengthy tender periods, eliminating delays following failed auctions, and reducing the duration of feasibility studies.
“For example, cutting long tender processes, excessively long studies, and the periods of inactivity that occur when an auction fails and must be re-tendered,” said Tri.
President Prabowo Subianto has set a target for Indonesia to complete the 100 GW solar power capacity within three years to ensure national energy independence.
The President highlighted that Indonesia’s current power generation capacity—utilising coal, oil, gas, and geothermal energy—stands at 88 gigawatts.
Through this development, the government aims to ensure the achievement of national energy independence and resilience.
Beyond energy independence, the construction of these power plants is expected to reduce state expenditure. The development of 100 GW of solar power could support electricity cost efficiencies of up to Rp73.9 trillion.