Bahlil Reveals Reasons Behind the Protracted Delays of the Masela Block Gas Project
Maluku, CNBC Indonesia — Energy and Mineral Resources Minister Bahlil Lahadalia has revealed that the Abadi Field project in the Masela Block has finally entered a new chapter, after being delayed for nearly three decades.
According to Bahlil, the project, which was planned 28 years ago, only reached the groundbreaking stage under the government of President Prabowo Subianto.
“Today, on 16 July, we mark a new chapter of the Abadi Masela project, which was initiated 28 years ago across six presidents. It is President Prabowo Subianto who can execute it today,” Bahlil said at the groundbreaking ceremony for the Abadi Field in the Masela Block, a National Strategic Project, on Thursday (16/7/2026).
Bahlil explained that for years the Abadi Field project was hampered by a prolonged debate over the development concept for the Liquefied Natural Gas (LNG) plant — whether it should be built offshore or onshore.
However, Prabowo ordered the immediate execution of the project and provided certainty for all oil and gas concessions and permits whose Plan of Development (PoD) had been completed but not yet implemented.
“On that basis, we sent a first warning letter to Inpex, and thank God, today we carry out the groundbreaking,” he said.
As is known, the Abadi Field in the Masela Block is a deep-sea gas field with Indonesia’s largest gas reserves, located around 160 kilometres off Yamdena Island in the Arafura Sea, at sea depths of 400-800 metres.
The Masela Production Sharing Contract (PSC), signed in 1998 and extended until 2055, has the potential to produce 9.5 MMTPA (million metric tonnes per annum) of LNG and 150 MMSCFD (million standard cubic feet per day) of piped gas. In addition, the Abadi Field is estimated to produce 35,000 barrels of condensate per day.