Bahlil Reveals Cause of Kalimantan Blackouts: Maintenance Issues
Jakarta, VIVA – Minister of Energy and Mineral Resources (ESDM), Bahlil Lahadalia, has spoken out about the electricity outages affecting several areas of Kalimantan.
He confirmed that the blackouts were not caused by an energy supply crisis. The disruptions relate to maintenance work on power plants and the electricity network currently being carried out by PT PLN (Persero).
“Well, according to information from PLN, it is related to maintenance. It is not an energy problem; there is nothing wrong with the energy supply,” Bahlil told journalists at the Presidential Palace complex in Central Jakarta on Tuesday, 4 August 2026.
He explained that, in addition to the maintenance work, PLN had also reported problems with the grid system, which had further affected the reliability of electricity supplies in a number of areas.
“So there is maintenance going on, and according to what PLN has said, it is also related to the network. But we will resolve it soon,” he said.
The explanation aligns with the statement issued by Iwan Soelistijno, General Manager of PLN’s Parent Distribution Unit for South and Central Kalimantan (Kalselteng). According to him, the outages occurred because three major power plants in South and Central Kalimantan were undergoing repairs simultaneously, reducing the electricity supply capacity feeding into the system.
At the SLK Gunung Mas coal-fired power plant in Central Kalimantan, one generating unit with a capacity of 100 megawatts (MW) is still in the recovery stage and is targeted to resume operations on 5 August 2026.
Meanwhile, the Tanjung Power Indonesia (TPI) coal-fired plant in Tabalong has already brought Unit 2, with a capacity of 100 MW, back online since 28 July 2026, ahead of the scheduled date.
At the Asam-Asam coal-fired plant in South Kalimantan, repairs are still ongoing. Unit 3, with a capacity of 54 MW, remains in the recovery stage, whilst Unit 2 is also still undergoing repairs.
The Governor of South Kalimantan, Muhidin, is optimistic that rolling blackouts can be halted from 5 August 2026, as a number of previously disrupted power plants begin to recover.
“God willing, from early August there will be no more blackouts, but we remain on standby,” said Muhidin.
Nevertheless, Muhidin estimates that the electricity system in South and Central Kalimantan will only return to full normality once repairs at the Asam-Asam plant are completed at the end of August 2026.