Avoid Traffic Jams Due to Jakarta-Tangerang Toll Road Repairs, Check the Schedule
JAKARTA – Reconstruction works on rigid pavements will resume on the Jakarta-Tangerang (Janger) Toll Road section to improve road infrastructure quality and user comfort.
Jasa Marga, through Jasamarga Metropolitan Tollroad as the operator of the toll road, along with PT Jasamarga Tollroad Maintenance (JMTM), will carry out maintenance work from 1 April to 8 April 2026.
The rigid reconstruction work will be conducted at several points, both towards Tangerang and towards Jakarta, with different implementation times at each location.
Here is the schedule for the rigid reconstruction work on the Jakarta-Tangerang Toll Road:
Towards Tangerang
Lane 2, KM 15+215 to 15+275 will be carried out starting Wednesday, 1 April 2026 at 06.00 WIB until Friday, 3 April 2026 at 05.00 WIB;
Lane 1, KM 16+615 to 17+320 at 3 work points, will be carried out starting Friday, 3 April 2026 at 06.00 WIB until Sunday, 5 April 2026 at 05.00 WIB;
Lane 2, On Ramp Karawaci 2 will be carried out starting Saturday, 4 April 2026 at 18.00 WIB until Monday, 8 April 2026 at 05.00 WIB;
Lane 2, KM 16+060 to 16+145 will be carried out starting Sunday, 5 April 2026 at 06.00 WIB until Tuesday, 7 April 2026 at 05.00 WIB.
Towards Jakarta
Lane 2, KM 25+105 to 25+005 will be carried out starting Wednesday, 1 April 2026 at 10.00 WIB until Friday, 3 April 2026 at 05.00 WIB;
Lane 2, KM 25+015 to 24+915 will be carried out starting Thursday, 2 April 2026 at 10.00 WIB until Saturday, 4 April 2026 at 05.00 WIB;
Outer shoulder lane and Lanes 1-2, Off Ramp Karang Tengah will be carried out starting Thursday, 2 April 2026 at 06.00 WIB until Saturday, 4 April 2026 at 05.00 WIB;
Lane 2, KM 24+455 to 24+395 will be carried out starting Friday, 3 April 2026 at 10.00 WIB until Sunday, 5 April 2026 at 05.00 WIB;
Lane 1, KM 25+080 to 24+870 at 4 work points, will be carried out starting Sunday, 5 April 2026 at 06.00 WIB until Tuesday, 7 April 2026 at 05.00 WIB;
Lane 1, KM 24+835 to 24+645 at 5 work points, will be carried out starting Monday, 6 April 2026 at 06.00 WIB until Wednesday, 8 April 2026 at 05.00 WIB.
Lane 1 and outer shoulder lane, inner, Off Ramp Karang Tengah will be carried out starting Monday, 6 April 2026 at 06.00 WIB until Wednesday, 8 April 2026 at 05.00 WIB.
During the work period, the lanes subject to reconstruction will be temporarily impassable. However, the other lanes will remain functional to support smooth traffic flow.