Asphalt and Cement Shortages Threaten to Delay Repairs to 20 Roads in West Nusa Tenggara
Repairs to nearly 20 road sections funded through the West Nusa Tenggara (NTB) provincial government’s 2026 revised regional budget are at risk of delay because asphalt and cement are in short supply.
“We are handling nearly 20 locations, but the obstacle is that asphalt supplies have not yet arrived,” said Lalu Kusuma Wijaya, head of the NTB Public Works, Spatial Planning and Housing Areas Agency (PUPRKP), when met at the NTB Governor’s Office on Tuesday (20 October 2026).
Wijaya said the NTB provincial government had set aside around Rp6 billion through the 2026 revised budget to repair 20 provincial road sections on Lombok and Sumbawa.
The works cover several strategic locations, including roads affected by flooding and landslides. These include sections along the Pusuk Sembalun route in East Lombok, the Tambora ring road in Dompu, Rabangodun in Bima City, and several locations in Bima Regency.
The asphalt shortage means asphalt producers, or Asphalt Mixing Plants (AMPs), have been unable to meet project requirements as usual. As a result, several repair projects that were ready to proceed have had to be postponed.
Wijaya estimated that asphalt supplies could return to normal in November. Even then, available supplies will also have to be shared with regency and city governments, which are facing project delays of their own.
“We can’t simply move quickly. We are ready; if everything is settled today or tomorrow, we can load the asphalt. That is really all it comes down to. If the material is available, we can proceed,” Wijaya said.
Nevertheless, Wijaya was optimistic that the supply problem would not push the works beyond the budget deadline, since the repair volumes at each location were relatively small.
“Hopefully it won’t be delayed, because the volume of work at each location isn’t that large. There are many separate spots, and we need to deal with them promptly,” he said.
Wijaya said asphalt surfacing was crucial to ensuring the quality of the work. Without an asphalt layer, repaired roads risk deteriorating quickly and prompting complaints from residents.
“Hopefully supplies will become available soon. If we repair a road but don’t immediately cover it with asphalt, it feels as though it hasn’t been repaired at all,” Wijaya stressed.
Cement had also been in short supply recently, but Wijaya predicted that distribution in NTB, known as Bumi Gora, was now gradually returning to normal.
“Cement supplies weren’t normal a few days ago, but they seem to have started moving normally this week,” Wijaya said.
The NTB provincial government has allocated around Rp6 billion for road maintenance in its 2026 revised budget. This supplements the Rp9 billion set aside for road works in the original regional budget.