Asam-asam Coal-Fired Power Plant Breakdown Worsens South Kalimantan Electricity Crisis
Rolling blackouts caused by the electricity crisis in South Kalimantan and Central Kalimantan continue. Damage to the machinery of the coal-fired Asam-asam steam power plant (PLTU) in Tanah Laut Regency has worsened the power crisis in the region.
The Governor of South Kalimantan, Muhidin, said he had received a report from PLN on the electricity crisis that has persisted in recent times.
“Based on the information we received from the General Manager of PLN, there is currently damage to the boiler of one of the Asam-asam PLTU units. Meanwhile, repairs to the gas and steam power plant (PLTGU) in Muara Teweh, Central Kalimantan, have not yet been completed,” Muhidin said on Monday (27/7).
This condition has further aggravated the electricity crisis in the South Kalimantan and Central Kalimantan power systems. “We ask the public to be patient in facing these blackouts. PLN is targeting that the plant repairs will be completed by early August and the electricity crisis can be resolved,” he said.
To minimise power outages, PLN has urged residents and industry to reduce electricity usage by up to 40 per cent. This efficiency in consumption is expected to reduce the extent and duration of the blackouts. For the past five days, PLN in the South Kalimantan–Central Kalimantan region has again been implementing rolling blackouts lasting 5–6 hours.
The blackouts have sparked a wave of public protests, as they are considered disruptive to daily activities and highly detrimental to the region’s micro, small and medium enterprises (MSMEs). Among them are protests from poultry farmers, who say many chickens and ducks have died as a result of the electricity crisis.
According to information gathered by the media, the dry season has also affected the water level of the Riam Kanan Reservoir, the raw water source for the Ir PM Noor hydroelectric plant in Banjar Regency. The 30-megawatt plant is currently operating only one 10 MW unit due to the limited reservoir water supply.
Source: jawawa.id (https://jawawa.id/newsitem/asam-asam-coal-fired-power-plant-breakdown-worsens-south-kalimantan-electricity-crisis-1785171082)
Originally published by Media Indonesia (https://mediaindonesia.com/nusantara/915337/pltu-asam-asam-rusak-krisis-listrik-di-kalsel-kian-parah), translated from Indonesian