Andre Rosiade Urges Acceleration of Lubuk Selasih-Surian Road Preservation

| Source: detikcom Translated from Indonesian | Infrastructure
Andre Rosiade Urges Acceleration of Lubuk Selasih-Surian Road Preservation
Image: detikcom

Andre Rosiade expressed his concerns during a coordination meeting with the West Sumatra National Road Implementation Agency (BPJN) and the Solok Regency Government at the BPJN West Sumatra office on Friday (5/6/2026). He noted that the project is vital for smoothing transportation flows in the southern region of West Sumatra.

Andre explained that the project involves the construction and upgrading of approximately 20 kilometres of road to a width of 11 metres. However, implementation currently requires support for the land acquisition of 142 affected houses along the road route.

“Securing central government funding is not easy. We must compete with other regions in Indonesia. Therefore, every budget successfully brought to West Sumatra must be utilised to its maximum potential so that the central government continues to provide development support in the future,” said Andre.

The Deputy Chairman of the Gerindra Party Faction in the House of Representatives (DPR RI) stated that the Rp 2_20 billion project represents a significant opportunity for Solok Regency and West Sumatra. Consequently, land acquisition issues must be resolved immediately to ensure development targets proceed as planned.

Andre hopes that once completed, the Lubuk Selasih-Surian road section will reach its full width of 11 metres, thereby enhancing safety, comfort, and the smooth flow of vehicles towards South Solok and surrounding areas.

Meanwhile, the Regent of Solok, Jon Firman Pandu, stated that the local government has prepared steps to accelerate the land acquisition process. According to the latest data, the number of affected buildings is 142 units, which is lower than the initial figure of 162 units.

“Alhamdulillah, almost all residents have expressed their agreement. The local government has also prepared a budget for the compensation of buildings affected by this project,” said Jon Firman Pandu.

He added that the asset valuation process by the Public Appraiser Office (KJPP) is currently underway and is targeted for completion in June 2026. Following this, compensation payments to residents will be processed immediately.

“Our target is that payments can begin in July, and by 31 August 2026 at the latest, the entire land acquisition process will be completed or ‘clean and clear’,” he said.

Jon also noted that three landslide points in the Air Dingin area are a priority for handling, as they significantly affect public transportation access.

The Head of BPJN West Sumatra, Elsa Putra Friandi, stated that his agency is awaiting the completion of land acquisition according to the agreed target. BPJN hopes that priority locations can be cleared quickly so that construction work can commence sooner.

Andre emphasised that the preservation project for the Lubuk Selasih-Surian road section is a crucial investment for the future of West Sumatra. In addition to increasing inter-regional connectivity, the project is expected to drive local economic growth and strengthen the distribution of goods and services in the southern part of West Sumatra.

More from 5 June 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/andre-rosiade-urges-acceleration-of-lubuk-selasih-surian-road-preservation-1780816636)
Originally published by detikcom (https://news.detik.com/berita/d-8519286/andre-rosiade-desak-percepatan-preservasi-jalan-lubuk-selasih-surian), translated from Indonesian
Print