Andre Rosiade Pushes for Acceleration of Land Acquisition for Padang-Sicincin Toll Road

| Source: detikcom Translated from Indonesian | Infrastructure
Andre Rosiade Pushes for Acceleration of Land Acquisition for Padang-Sicincin Toll Road
Image: detikcom

Deputy Chairman of Commission VI of the Indonesian House of Representatives, Andre Rosiade, stated that land acquisition is the primary key to the construction of the Padang-Sicincin toll road section. Andre does not want the delays in previous toll road projects in West Sumatra to be repeated due to land issues.

Andre conveyed this during the Preliminary Meeting for the Preparation of the Pekanbaru-Padang Toll Road Section: Bukittinggi-Padang Panjang-Sicincin at the West Sumatra Attorney General’s Office, Jalan Raden Saleh, Padang, on Thursday (9/4/2026). The meeting was held together with the Head of the West Sumatra Attorney General’s Office, Muhibuddin, and facilitated by the Head of the National Road Implementation Centre (BPJN) of the Ministry of Public Works West Sumatra, Elsa Putra Friandi.

The meeting was attended by West Sumatra Governor Mahyeldi, President Director of Hutama Karya Koentjoro, Head of the West Sumatra ATR/BPN Regional Office Teddi Guspriadi, as well as regional heads whose areas are traversed by the toll road route. Also present were Regent of Padang Pariaman Jon Kennedy Azis, Regent of Tanah Datar Eka Putra, Mayor of Bukittinggi Ramlan Nurmatias, Deputy Mayor of Padang Panjang Alex Saputra, and Secretary of Agam Regency Muhammad Lutfi. The Attorney General’s Office also brought in the heads of district attorneys in the areas traversed by the toll road route.

“Our homework is just one: land acquisition. The reason we are holding this meeting today is to anticipate this. Because in West Sumatra, the problem is always land,” said Andre.

Andre compared the progress of toll road construction in West Sumatra with other regions. He mentioned that the Pekanbaru-Dumai section, spanning 131 kilometres, was completed much faster than the 36-kilometre Padang-Sicincin section, which was only finished several years later.

“As a result, the central government assessed West Sumatra as no longer attractive for toll road development. Therefore, we worked hard to convince the President and the Minister of Public Works to continue the Sicincin section to Bukittinggi,” he stated.

This Deputy Chairman of the Gerindra Faction in the House of Representatives committed to President Prabowo that this project could be completed before 2029. He urged all regional heads to seriously assist in accelerating land acquisition.

“We only have one year to ensure this land acquisition process runs smoothly. We must prove that West Sumatra is capable of resolving land issues,” he emphasised.

Andre revealed that the continuation project of the Sicincin-Bukittinggi toll road is worth around Rp25.6 trillion and is very important for driving economic growth in West Sumatra, which is currently still low.

“West Sumatra’s economic growth is only around 3 percent, even potentially dropping to 2.5 percent. We need large investments to enter this region,” he said.

Meanwhile, Muhibuddin affirmed that his side is ready to fully oversee the land acquisition process to ensure it runs according to target. Based on the compiled timeline, after the location determination in September 2026, land acquisition is targeted to take place until June 2027, with a 60 percent achievement by January 2027.

“We are ready to oversee 24 hours as the state’s attorney. If there are legal obstacles related to land acquisition, please coordinate with us. Do not let this project stop just because of administrative issues,” said Muhibuddin.

Muhibuddin stated that the land acquisition process will be carried out juridically and sociologically so that community rights remain protected without hindering development interests.

Meanwhile, Head of the West Sumatra ATR/BPN Regional Office Teddi Guspriadi said that the land acquisition stages begin with the preparation of the Land Acquisition Planning Document (DPPT) from April to June 2026. This will then be followed by location determination in September 2026. According to him, socialisation is important from the start to the community to avoid conflicts in the implementation stage.

“Do not let any entitled party be unaware that their land is affected. Socialisation is the key to a smooth process,” he said.

West Sumatra Governor Mahyeldi affirmed the full support of the regional government for accelerating the construction of the Sicincin-Bukittinggi toll road. He asked all regional heads to actively approach the community so that the land acquisition process runs without obstacles.

“We do not want the delays that occurred previously to happen again. Land acquisition is the main key to the continuation of this toll road development,” said Mahyeldi.

Mahyeldi emphasised that toll road development is an important factor in driving the mobility of goods and services as well as economic growth in West Sumatra.

In addition to accelerating land acquisition, the meeting also presented the technical readiness of the project by Hutama Karya. President Director of Hutama Karya Koentjoro stated that the feasibility study (FS) has been completed and discussed.

Tracking of the route survey in the Barisan Wildlife Reserve area has been carried out together with the BKSDA. Currently, route and topography surveys are still ongoing, including the permitting process in wildlife reserve and protected forest areas.

Basic design and preparation of the ROW plan are targeted to take place throughout 2026 to early 2027. Environmental documents such as AMDAL and Andalalin are also being prepared in the same period.

In terms of forestry area permitting, the ongoing processes include approval for technical geological survey activities and cooperation with the Directorate General of KSDAE in wildlife reserve areas, as well as approval for survey activities and use of protected forest areas through the Directorate General of Forestry Planology.

Overall, construction of the Bukittinggi-Padang Panjang section is targeted for completion in the first quarter of 2029, while the Padang Panjang-Sicincin section is planned to be finished in the second quarter of 2031. This project is expected to be the main driver of connectivity and economic growth in West Sumatra through the continuation of the Trans-Sumatra Toll Road network.

More from 9 April 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/andre-rosiade-pushes-for-acceleration-of-land-acquisition-for-padang-sicincin-toll-road-1775735458)
Originally published by detikcom (https://news.detik.com/berita/d-8436842/andre-rosiade-dorong-percepatan-pembebasan-lahan-tol-padang-sicincin), translated from Indonesian
Print