Andre Rosiade Inspects Malalak Road Construction in West Sumatra with Head of BPJN West Sumatra

| Source: detikcom Translated from Indonesian | Infrastructure
Andre Rosiade Inspects Malalak Road Construction in West Sumatra with Head of BPJN West Sumatra
Image: detikcom

The inspection took place on Sunday (10/5/2026). Attending the event were Agam Regency DPRD member Novi Irwan, Malalak Ulya Sub-district Head Satar, village heads, clan elders, and local community figures.

At the inspection site, Andre emphasised that the central government is committed to addressing the Malalak road in stages using state budget funds. He urged the public not to worry about rumours of reduced development funding in the disaster-affected area.

“President Prabowo’s government, through the Ministry of Public Works, is committed to completing this road. Although it is a provincial road under the governor’s authority, due to limited regional funding, the central government is assisting with its completion using the state budget,” Andre stated.

Andre mentioned that the total budget prepared by the central government for handling the Malalak road amounts to approximately Rp670 billion. The work is being carried out in stages, starting with emergency handling up to permanent construction.

“Insyaallah, the first phase will be completed in August. After that, it will proceed to the second phase through a tender process, including the construction of a bridge at kilometre 82. So, the public need not worry; development will continue,” he said.

According to Andre, the development of West Sumatra must be carried out collaboratively between the central government, regional government, and all stakeholders.

“Building West Sumatra must be done together. If we work together, insyaallah, development will be realised. We cannot go it alone,” he stated.

Head of BPJN West Sumatra Elsa Putra Friandi explained that the initial handling of the Malalak road is being carried out using an emergency response mechanism in accordance with the Minister of Public Works’ instructions. As the provincial government’s emergency status lasts until September 2026, the work is divided into several phases to comply with procurement regulations.

“Work that can be completed before September is being handled through the ongoing contract by PT HKI. Subsequent work will be re-tendered. So, the budget is not lost, but the implementation process is divided to align with the emergency mechanism,” Elsa said.

Elsa assured that points on the road that were previously cut off are now reconnected, although usage is still limited for public safety. BPJN is also keeping heavy equipment on standby at the site to anticipate bad weather and potential follow-up landslides.

“The equipment remains on standby at the location until permanent handling is complete. Later, the road will also be tidied up and given a gravel surface so it is not too slippery in the rain,” she said.

Elsa added that the Malalak route is currently prioritised for local residents. Meanwhile, vehicles from outside the area are advised to use alternative routes because the road conditions are not yet fully safe.

“For locals, it is still passable. But if it rains, it is best to avoid it because it is still dangerous. For vehicles from outside the area, they are temporarily advised to take alternative routes,” she stated.

Malalak community figure and Agam DPRD member Erdinal expressed appreciation for Andre’s attention to development in Malalak, including road handling and BTS tower construction in blank spot areas.

“We hope the allocated budget for Malalak continues and the road development can be completed soon because our region is highly vulnerable,” he said.

Agam Deputy Regent M Iqbal also thanked Andre Rosiade for his attention to Agam Regency, particularly in post-disaster handling in Malalak Sub-district.

“Mr Andre has greatly helped West Sumatra, including Agam Regency. From infrastructure and post-disaster aid to BTS development in blank spot areas like Malalak. We hope this attention continues because Agam still needs much support from the central government,” M Iqbal said.

More from 10 May 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/andre-rosiade-inspects-malalak-road-construction-in-west-sumatra-with-head-of-bpjn-west-sumatra-1778424678)
Originally published by detikcom (https://news.detik.com/berita/d-8483389/andre-rosiade-tinjau-pembangunan-jalan-malalak-sumbar-bareng-kepala-bpjn-sumbar), translated from Indonesian
Print