AHY: Kemang Pratama Bridge in Bekasi Designed to Withstand Flooding
Image: Antara (Indonesian)

Bekasi (ANTARA) – Coordinating Minister for Infrastructure and Regional Development Agus Harimurti Yudhoyono (AHY) said the rebuilt Kemang Pratama Bridge in Rawalumbu, Bekasi City, has been designed without pillars to withstand natural hazards, particularly flooding.

AHY inspected construction of the rebuilt bridge in Rawalumbu district, Bekasi City, after it was severed by flooding in March 2025.

“I commend the Public Works Minister and his team for swiftly rebuilding this vital infrastructure. The provincial government and the mayor have overseen the work, and the community has also helped, enabling the bridge to reopen and make travel easier,” AHY said in Bekasi on Friday.

He said the bridge had been rebuilt with a new concept and design to make it safer and more robust. Unlike the old structure, which had a supporting pier in the middle, the new bridge has a pillar-free span of nearly 80 metres.

The design change is intended to prevent rubbish carried downstream from accumulating against the bridge and creating excessive pressure when water levels rise. The bridge has also been raised to provide safe clearance above the water during the highest flood levels.

The Rp60 billion bridge, funded through the Regional Road Presidential Instruction (IJD) programme, has passed load testing. Trials using a convoy of heavy vehicles demonstrated that the structure could withstand a load of up to one tonne per square metre.

AHY said he hoped the restored route would make daily travel easier. The project reflects President Prabowo Subianto’s direction that essential infrastructure should deliver tangible improvements in safety and comfort, while creating new economic opportunities for the public.

He also said he hoped the new infrastructure would withstand natural hazards, given forecasts of heavier rainfall towards the end of the year. However, flood management also depends on preparedness in upstream areas.

“What we do downstream depends greatly on what happens upstream. If there is environmental damage, misuse of land, a reduction in water catchment areas, sedimentation or careless rubbish disposal, the people of Bekasi downstream will inevitably feel the impact,” he said.

Gatot Sukmara, acting director of bridge development at the Ministry of Public Works, said construction of Kemang Pratama Bridge would take 300 calendar days, or 10 months, from October 2025 to August 2026. The maintenance period will end in August 2027, before the bridge is formally handed over.

The project covers 410 metres, including a 78-metre span and a width of nine metres. It also includes 332 metres of rigid pavement and asphalt surfacing.

Gatot said he was confident the bridge would reduce journey times and congestion, while connecting key facilities including hospitals, schools and government offices.

“ Kemang Pratama Bridge is also designed to reduce obstruction to water flow from debris and increase clearance over the river. As well as improving residents’ mobility, it will help minimise the impact of flooding,” he said.

More from 30 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/ahy-kemang-pratama-bridge-in-bekasi-designed-to-withstand-flooding-1793346756)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5821363/menko-ahy-jembatan-kemang-pratama-bekasi-didesain-antisipasi-banjir), translated from Indonesian
Print