Agreed Revisions to the Andaman Block Gas PoD
The Aceh Provincial Government and the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) have agreed to revise the Plan of Development (PoD), the planning document for managing gas discoveries in the Tengkulo area within the South Andaman Block, Aceh.
“They (SKK Migas) are willing to accommodate the PoD revision that we will submit,” said Aceh Provincial Government Spokesperson, Nurlle Effendi, when confirmed from Banda Aceh on Thursday, 11 June 2026.
The agreement to revise the PoD, signed by Aceh Governor Muzakir Manaf (also known as Mualem) and the Head of SKK Migas, Djoko Siswanto, was prominent during their meeting at the SKK Migas office in Jakarta last Wednesday.
Previously, the Governor of Aceh had written to the Minister of Energy and Mineral Resources (ESDM) requesting that the processing of gas discovered by Mubadala Energy not be conducted via the FPSO (floating production, storage, and offloading) scheme or offshore processing. Instead, the Aceh Provincial Government requested that the gas be processed via an onshore receiving facility (ORF) located at the Arun Lhokseumawe Special Economic Zone (KEK).
In the letter, the Governor also requested that the allocation of Mubadala’s gas be utilised for industries within Aceh. Furthermore, the letter included a request for a temporary postponement of the PoD due to ongoing differences in opinion between the central government and the Aceh administration.
Nurlis explained that the Governor of Aceh does not reject the Tengkulo gas field project in South Andaman or Mubadala Energy as the investor, but rather seeks improvements to the PoD.
Fundamentally, the Aceh government strongly supports the investment climate and has consistently encouraged capital investment to grow the economy of the region. “However, there are several aspects of the PoD that need to be improved so that Aceh does not suffer a disadvantage,” said Nurlis.
Initial Scenario
According to the PoD established by the Ministry of ESDM and SKK Migas in March 2026, gas and condensate were to be processed using an FPSO scheme in South Andaman, before being distributed to the Onshore Receiving Facilities (ORF) located in the Arun KEK, Lhokseumawe, via pipelines from the FPSO to the ORF.
Mubadala Energy is currently preparing a tender process for a giant FPSO unit to accelerate the commercialisation of gas (fast-track) in the South Andaman block.
He explained that the unit is projected to process deep-sea gas before being piped through. An FPSO serves a full range of functions, producing or processing oil and gas directly on the vessel while simultaneously storing and distributing it.