After Trader Relocation, Malang City Government Gradually Rehabilitates Pasar Gadang Roads

| Source: Tempo (Indonesian) Translated from Indonesian | Infrastructure

The Malang City Government began the phased rehabilitation project for the Gadang-Bumiayu and Pasar Gadang roads on 15 June 2026. This approach was implemented to ensure that community activities can continue uninterrupted during the construction process.

The road rehabilitation work follows the completion of the relocation of traders from the Gadang Central Market (PIG) as part of an area redevelopment initiative. This step serves as the initial phase of urban order and the optimisation of market and road functions, which will be followed by the demolition of old stalls.

The acceleration of this relocation was prompted by the availability of budget support from the central government through a Special Allocation Fund (DAK) amounting to Rp14.9 billion, earmarked for road infrastructure development. This budget will be utilised for the construction of two main road sections, including repairs to road conditions that have long been a source of public complaint due to damage and flooding.

The Mayor of Malang, Wahyu Hidayat, has confirmed that the relocation process proceeded smoothly and has been fully completed. Approximately 1,200 traders, many of whom had been trading in the area for decades, were relocated.

To prevent street vendors (PKL) from returning along the roadside, the Malang City Government has implemented an area management plan involving the installation of higher boundary fences supplemented with greenery as an additional barrier. “There will be high fences, followed by plants, then the road and pavement. This ensures there is no space for vehicles to stop or for trading on the roadside,” said Wahyu.

The redevelopment of the Pasar Gadang area is expected to optimise road functions, improve order, and address the community’s long-standing demand for area improvements. The Head of the Malang City Department of Public Works, Spatial Planning, Housing, and Settlement Areas (DPUPRPKP), Dandung Djulharjanto, explained that the road rehabilitation begins with the construction of drainage for the southern side of the Gadang–Bumiayu road from the eastern direction, before proceeding to road construction.

Once that section is completed and functional, work will move to the northern side following the same stages. “The existing lanes will continue to be utilised for now. Once the southern side is finished, traffic will be diverted to the new road, and then the northern side will be worked on. With this scheme, the public will maintain access throughout the construction process,” he stated.

A similar scheme is being applied to the rehabilitation of Pasar Gadang Road to ensure that access to and from the area remains available during the works. Dandung explained that the construction of 1x1 metre drainage is intended to increase the capacity of the channels in the area.

After the drainage work is complete, road construction will proceed using rigid concrete for most sections, while other segments will use asphalt layers. “Once the work on both sides is finished, the final stage will be paving, starting from the western bridge to the Bumiayu intersection,” said Dunning.

Upon completion, this rehabilitation will transform the Gadang–Bumiayu road into a dual carriageway, with each section measuring 7.5 metres in width. Meanwhile, the electricity poles currently located in the middle of the road will not be moved, as they have been accommodated within the design of the road median.

More from 19 June 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/after-trader-relocation-malang-city-government-gradually-rehabilitates-pasar-gadang-roads-1781870134)
Originally published by Tempo (Indonesian) (https://nasional.tempo.co/read/2109412/usai-relokasi-pedagang-pemkot-malang-bertahap-rehabilitasi-jalan-pasar-gadang), translated from Indonesian