After Groundbreaking, a New Chapter for Japan’s Giant Gas Project in Indonesia
Jakarta, CNBC Indonesia – The giant liquefied natural gas (LNG) project in Maluku, the Abadi LNG project in the Masela Block, has made further progress following its groundbreaking by President Prabowo Subianto in July 2026.
The project, estimated to require US$20.9 billion in investment, has now completed its Front-End Engineering Design (FEED) phase.
SKK Migas head Djoko Siswanto said FEED for the Abadi LNG project was completed three months ahead of the target set for the end of 2026.
“INPEX was initially expected to complete FEED at the end of this year. We kept meeting almost every week so that it could be completed sooner. Thankfully, it has now been completed three months ahead of target, as of today,” Djoko said in a speech at the Abadi LNG Project FEED Completion Ceremony in Jakarta on Tuesday (27 October 2026).
He said the FEED work covered four main areas, including Subsea Umbilicals, Risers and Flowlines (SURF) and the Gas Export Pipeline, undertaken by PT World Sea Indonesia.
The second area was FEED for the Floating Production Storage and Offloading (FPSO) facility, involving two contractor groups: a consortium of PT Saipem, PT Tripatra, PT McDermott and PT Teknif Indonesia, as well as PT JGC Indonesia.
FEED for the Onshore LNG (OLNG) plant was carried out by two consortiums: one comprising JGC and Teknif, and another comprising PT KBR, Samsung and PT Adhi Karya (Persero).
“Given the complexity and scale of the work, the FEED process was certainly not easy. However, through our collaboration and joint efforts, it was completed ahead of the overall schedule,” he said.
“The quality of the FEED was also strengthened by an Independent Design Review involving more than 200 subject-matter experts, including professors and doctors, and three universities: Pattimura University, Sepuluh Nopember Institute of Technology and Bandung Institute of Technology. Thank you, and a round of applause for these three institutions,” he said.
On gas allocation, he said Energy and Mineral Resources Minister Bahlil Lahadalia had approved the allocation from the Masela LNG plant for both domestic use and exports.
Domestic buyers are PT PLN (Persero), PT PGN Tbk and PT Pupuk Indonesia (Persero).
For exports, the minister has approved gas allocations for Singapore. This was formalised through the signing by Bahlil of approvals for LNG exports from the Masela plant to BP Singapore and Shell Singapore.
“Thankfully, yesterday and the day before, the minister also signed approvals for domestic gas allocations, including pipeline gas for Pupuk Indonesia and PLN, and LNG for PGN,” Djoko said.
“Yesterday, the minister also signed the approval for LNG exports to BP Singapore and Shell Singapore. Although we have reduced the volume slightly, we remain committed to exporting substantial volumes to Singapore,” he said.
He said he hoped the Masela LNG project’s Gas Sales and Purchase Agreement (GSPA) could be signed the following day, Wednesday (28 October 2026), at the 2026 Upstream Oil and Gas Economic, Financial and Commercial Forum (FOREK).
“Hopefully, the GSPA will be signed tomorrow at FOREK, and the minister has confirmed his attendance,” he said.
Once the GSPA is signed, the Masela LNG plant’s final investment decision (FID) is expected to be made by the end of this year or, at the latest, in January 2027.
“The GSPA is also a key requirement for the INPEX, Pertamina and Searah consortium to complete, approve or sign its FID,” he said.
“Hopefully, the FID will follow soon, ideally by the end of this year or, at the latest, in January 2027,” he added.
INPEX Masela Ltd President Director Kenji Hasegawa, who also spoke at the event, said the FEED phase covered the Onshore LNG (OLNG) plant, Floating Production Storage and Offloading (FPSO) facility, Subsea Umbilicals, Risers and Flowlines (SURF), and Gas Export Pipeline (GEP).
“Ladies and gentlemen, the Abadi LNG project plays an important role in supporting Indonesia’s long-term energy security, strengthening natural gas supplies and creating economic opportunities for future generations. With this phase complete, we are now focused on reaching the next milestones,” Kenji said.
“I should emphasise that completing this phase is not our final objective. We are now moving towards the Engineering, Procurement, Construction and Installation (EPCI) stage, while preparing for the final investment decision,” he said.
“Achieving these milestones will require continued coordination and commitment from all parties. INPEX remains committed to working closely with the government, joint-venture partners, contractors and other stakeholders to advance the project safely and responsibly,” he said.
“Thank you to everyone who contributed to this achievement. We look forward to further strengthening our collaboration as the Abadi LNG project moves into its next development phase, for the benefit of Indonesia,” he concluded.
About the Masela Block
The project, with an investment value of US$20.95 billion, is estimated to hold 6.97 trillion cubic feet (TCF) of gas.
Gas from the Masela Block will be processed into LNG at an onshore plant with production capacity of 9.5 million tonnes per annum (MTPA). The block is also expected to produce 150 million standard cubic feet per day (MMSCFD) of pipeline gas and 35,000 barrels per day (bpd) of condensate.
The project has long been awaited by Indonesians. INPEX Corporation, operator of the Masela Block, signed its production-sharing contract (PSC) with the Indonesian Government on 16 November 1998, during President BJ Habibie’s administration.
Nearly 30 years after the contract was signed, the project has yet to begin operations or produce oil and gas for Indonesia.
The Masela Block PSC has been extended for 20 years, plus a further seven years, until 2055. The extension of INPEX’s contract was signed in October 2017, when Ignasius Jonan was Energy and Mineral Resources Minister. INPEX’s contract was originally due to expire in 2028, after a 30-year term with the Indonesian Government.
Because the project had not entered operation and INPEX remained committed to developing it, the Indonesian Government granted a 20-year extension from 2028, plus seven additional years after changing the LNG plant’s planned location from offshore to onshore.
INPEX Masela Ltd holds the largest participating interest (PI) in the Masela Block, at 65%.
INPEX was previously partnered by Shell Upstream Overseas Services, which held a 35% stake. Shell later decided to withdraw from the long-awaited gas project in Maluku.
In July 2023, Shell’s 35% stake was acquired by PT Pertamina Hulu Energi through its subsidiary PT Pertamina Hulu Energi Masela (PHE Masela), which took 20%, while Petronas acquired 15%.
The sale and purchase agreement for the participating interests from Shell to Pertamina and Petronas was signed on 25 July 2023, and the Energy and Mineral Resources Minister approved the transfer on 4 October 2023.
The Abadi field in the Masela Block is a deep-water gas field with Indonesia’s largest gas reserves. It is located about 160 kilometres off Yamdena Island in the Arafura Sea, at water depths of 400–800 metres. The field is estimated to contain 6.97 TCF of gas.
After the PSC was signed in 1998, INPEX discovered the giant gas reserves in the Masela Block in 2000.
Nineteen years later, the Indonesian Government approved INPEX’s first Plan of Development (PoD-I), allowing production of 9.5 MTPA of LNG from the Masela plant, along with 150 MMSCFD of pipeline gas and 35,000 bpd of condensate.
Developing this complex, high-risk greenfield oil and gas field will involve deep-water drilling, subsea facilities, an FPSO and an onshore LNG plant. These challenges also represent a major opportunity for INPEX and its partners to deliver the project. Development could also employ up to 10,000 people.
The Masela Block is also planned to produce cleaner energy through carbon capture and storage (CCS), supporting the government’s efforts to reduce carbon emissions and promote sustainability during the energy transition.
The Indonesian Government approved the CCS plan on 28 November 2023 through the second revision of PoD-I. The project then proceeded to FEED tendering. INPEX launched FEED for the OLNG plant on Wednesday, 9 April 2025.
Source: jawawa.id (https://jawawa.id/newsitem/after-groundbreaking-a-new-chapter-for-japans-giant-gas-project-in-indonesia-1793105500)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20261027183157-4-779973/usai-groundbreaking-ini-babak-baru-proyek-gas-jumbo-jepang-di-ri), translated from Indonesian