Adhi Karya Completes MRT Jakarta Phase 2A Tunnel Excavation
Jakarta (ANTARA) – PT Adhi Karya (Persero) Tbk (ADHI) has completed all tunnel excavation using tunnel-boring machines (TBMs) on the MRT Jakarta CP202 project in Phase 2A. The work was completed when TBM-2 broke through at the South Shaft of Mangga Besar Station.
“The breakthrough marks the completion of all TBM tunnel excavation work on the CP202 package, carried out by ADHI and Shimizu Corporation through the Shimizu-Adhi Joint Venture (SAJV),” PT Adhi Karya President Director Moeharmein Zein Chaniago said in Jakarta on Friday.
He praised the quality of the construction work after ADHI management conducted an inspection of the MRT Jakarta CP202 project site.
According to him, the work on site demonstrated high construction standards, supported by orderly work arrangements and the implementation of occupational safety measures.
“We saw work of an exceptional standard, carried out in a very orderly manner. The quality was also very high, including the application of safety measures,” Moeharmein said.
He said this reflected Adhi Karya management’s commitment to ensuring that every project prioritises quality, workplace safety and the timely execution of construction.
The completion of the tunnel excavation is a significant achievement given the complexity of the underground construction, which reached depths of up to 30 metres.
Moeharmein said the work required careful planning, innovation and intensive coordination between Adhi Karya and Shimizu Corporation to ensure every stage was completed in line with the required standards.
The company also prioritised operational excellence, with a focus on the effectiveness and efficiency of project delivery.
The cooperation between management and the project team, he said, also reflected the application of ADHI employees’ Learner, Adaptive, Militant, Problem Solver (LAMPs) characteristics, particularly adaptability.
“This is demonstrated by the ability to face construction challenges through collaboration, innovation and adapting to the complexity of work on site,” Moeharmein said.
He added that, beyond the technical achievement, TBM-2’s breakthrough formed part of Adhi’s contribution to the development of public transport in Jakarta.
He hoped the construction of MRT Jakarta Phase 2A would strengthen connections between areas, provide more efficient and integrated mobility, and support sustainable urban infrastructure development.
“By completing the tunnel excavation work on the CP202 package, ADHI is once again contributing to the development of strategic national infrastructure, particularly mass transport as a pillar of future mobility,” Moeharmein said.
Source: jawawa.id (https://jawawa.id/newsitem/adhi-karya-completes-mrt-jakarta-phase-2a-tunnel-excavation-1793958703)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5836591/adhi-karya-tuntaskan-penggalian-terowongan-mrt-jakarta-fase-2a), translated from Indonesian