Aceh post-disaster recovery to enter rehab and reconstruction phase in August 2026

| Source: Antara (Indonesian) Translated from Indonesian | Infrastructure
Aceh post-disaster recovery to enter rehab and reconstruction phase in August 2026
Image: Antara (Indonesian)

The Task Force for the Acceleration of Rehabilitation and Reconstruction (Satgas PRR) for Sumatra has announced that the post-disaster recovery in Aceh Province will enter the rehabilitation and reconstruction phase beginning in August 2026. Safrizal ZA, Head of the Aceh Regional Post for the Sumatra PRR Task Force, stated in Banda Aceh on Friday that the phase will be officially determined at the end of July, following the completion of the emergency alert, emergency response, and emergency response transition stages. “Shortly, Aceh’s post-disaster recovery will leave the emergency response stage and move towards the post-disaster or rehabilitation and reconstruction phase. On 30 July, it will be decided to enter the rehabilitation and reconstruction phase,” he said.

Safrizal noted that several indicators have been met for the government to consider this transition. These include the full restoration of governance in affected areas, with all government functions now operational despite some village offices suffering severe damage. “For instance, in the services in Aceh Tamiang Regency, which was severely impacted by hydrometeorological disasters, they have recovered. IPDN cadets were deployed for two months in the regency to restore government infrastructure,” he said. Public health services have also returned to normal, although some community health centres are operating from official residences while their buildings undergo rehabilitation.

Educational services have similarly recovered, with teaching and learning activities proceeding smoothly, even though some damaged schools are temporarily using other buildings. A total of 3,120 school units were affected by the hydrometeorological disasters in Aceh, and 41 schools have been relocated, but all school activities have resumed. Land transportation access has been restored, with all roads now functional and in use, and these routes will be further upgraded during the rehabilitation and reconstruction phase. From an economic perspective, market activities have returned to normal, with the majority of the 127 affected markets now operating again, indicating that community economic activity has largely normalised, though not yet fully recovered.

Safrizal said the current focus is on completing the construction of permanent housing. The construction progress has reached 4.9 percent, with 401 units completed out of a total of 37,373 units. “This year, an initial budget of around Rp2 trillion has been allocated for the first phase of permanent housing construction. There are two categories of permanent housing being built: communal and in-situ. The requirement is that they must be built in safe zones,” he said.

More from 24 July 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/aceh-post-disaster-recovery-to-enter-rehab-and-reconstruction-phase-in-august-2026-1784894136)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5664509/pemulihan-aceh-pascabencana-masuk-fase-rehab-rekon-mulai-agustus-2026), translated from Indonesian
Print