Aceh Experience Offers Useful Lessons for Manila Rebuilding Effort

| Source: Financial Times

The Financial Times (UK) By Ben Bland in Jakarta

photo: Reconstruction work in Banda Aceh, Indonesia. Ulet Ifansasti/Getty Images

Nine years after the Indian Ocean tsunami devastated the Indonesian province of Aceh, a fishing boat still sits on the roof of a destroyed house in the suburbs of Banda Aceh.

On the other side of the provincial capital, a large ship remains several miles inland where the huge tidal wave deposited it.

These are not relics of yet another failed international relief effort. On the contrary, they are testament to one of the biggest aid operations the world has seen in a developing country.

Both vessels have been left behind as part of a “tsunami tourism trail” designed to help residents cope with the psychological damage and generate much needed income.

As Benigno “Noynoy” Aquino, the Philippines president, on Sunday pledged a swift recovery from Typhoon Haiyan during a visit to Guiuan, one of the areas hardest hit by the catastrophe, the Aceh experience offers some useful lessons for Manila.

The 10m-30m waves that smashed into Aceh on Boxing Day 2004 wreaked unprecedented havoc. More than 130,000 people were killed and more than 600,000 displaced as houses, schools and roads were wiped out across a province that was already suffering because of a decades-long separatist conflict.

The disaster prompted an unparalleled humanitarian response and Aceh has become a model for reconstruction operations because of what went right and what went wrong.

“After four years, more than 90 per cent of the rehabilitation and construction was complete and over 90 per cent of the aid money that was pledged [$7.2bn] had been spent,” says Said Faisal, who was the deputy head of the Indonesian government’s specially established Rehabilitation and Reconstruction Agency (BRR) for Aceh until it completed its work in 2009.

It took three months to clear all the debris and decaying human bodies, before the real reconstruction efforts could begin.

Within four years, the government, aid agencies, international groups and local residents had rebuilt 140,000 houses, reclaimed nearly 70,000 hectares of agricultural land and retrained more than 100,000 people.

But, despite the large pools of cash and goodwill, there were no quick fixes and many slip-ups.

“Everything was hard,” says Mr Faisal, who is now managing the regional response to Typhoon Haiyan as the head of the Association of Southeast Asian Nations’ disaster response unit.

As hundreds of organisations and thousands of relief workers poured into Aceh, the situation on the ground became chaotic.

Sensing the need for co-ordination, President Susilo Bambang Yudhoyono established the BRR as a ministry-level agency to align the international response with the different parts of the Indonesian government.

However, the work of many aid agencies overlapped, especially in easy to reach Banda Aceh, where several competed to offer the same services – from water supplies to fishing boat construction.

With governance weak and corruption rife, there were many cases of graft, waste and slipshod work as agencies rushed to dole out their cash. Save the Children was one of several NGOs that had to completely rebuild hundreds of homes after its contractors used substandard construction methods.

Last year, John McCarthy, a development specialist at Australian National University, surveyed more than 40 Aceh villages that had each hosted between seven and 10 NGO projects to promote new livelihoods. Only four projects were still running and about half the residents were still suffering from food insecurity.

He believes aid agencies need to scale back their ambitions when responding to major disasters, arguing in a blog post for Australia’s Development Policy Centre that “rather than trying to ‘build back better’, they might just aim to help return people to adequate livelihoods”.

While governments and NGOs are often criticised for their slow response to major disasters, aid workers say such large relief operations face unavoidable problems.

In Aceh, as will be the case in the Philippines, there were inherent tensions between rebuilding homes quickly and constructing them to higher standards, and between importing international expertise and distorting the local economy.

During the reconstruction phase, annual price inflation in some parts of Aceh soared to more than 40 per cent because of the high costs of bringing in materials with so much basic infrastructure knocked out.

In the face of so many challenges, relief organisations were forced to take a more nimble approach.

“It’s not about managing the risk but living with the risk on a day-to-day to basis,” says Mr Faisal.

With the physical, psychological and economic landscape altered so drastically, it is impossible to return to the status quo, says Iwan Gunawan, the World Bank’s senior disaster risk management specialist in Indonesia.

“Some gain and some lose,” he says. “The question is not, have people fully recovered, but are they on the right track in terms of a sustainable livelihood.”

sidebar: Aceh rehabilitation in numbers:

Aid pledged: $7.2bn

140,304 houses rebuilt

155,182 labourers trained

69,979 hectares of land reclaimed

7,109 fishing boats built or distributed

3,696km of road constructed

1,759 schools built

Source: Rehabilitation and Reconstruction Agency (BRR)

More from 17 November 2013 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/aceh-experience-offers-useful-lessons-for-manila-rebuilding-effort-1384621200)
Originally published by Financial Times (http://www.ft.com/cms/s/0/d9ee491c-4def-11e3-8fa5-00144feabdc0.html#axzz2kubbBDmK)
Print