A Week After Flores Earthquake, Public Works Ministry Handles 34 Landslide Points and 9 Bridges

| | Source: Republika Translated from Indonesian | Infrastructure
A Week After Flores Earthquake, Public Works Ministry Handles 34 Landslide Points and 9 Bridges
Image: Republika

The Ministry of Public Works (PU) is continuing to handle infrastructure affected by the NTT earthquake. Public Works Minister Dody Hanggodo said the ministry’s team has inspected dozens of landslide points and bridges on several national road sections, while also carrying out clearing, securing, and preparing permanent handling at damaged locations.

“Based on initial data collection by the East Nusa Tenggara National Road Implementation Agency (BPJN), 94 road and bridge points were recorded as damaged by the earthquake, consisting of 75 landslide points, three subsidence points, and 16 bridges and culverts,” Dody said in a written statement in Jakarta on Sunday (23/8/2026).

Of that number, Dody said, the Directorate General of Highways’ Disaster Emergency Response Task Force Team has conducted field inspections at 34 landslide points and nine bridges/culverts. Dody said that since the first day of the earthquake, he has instructed the agency offices in the NTT region to increase preparedness and provide full support in post-disaster handling.

“The readiness of personnel, heavy equipment, and coordination with local governments are important parts of ensuring that affected infrastructure can be restored immediately,” Dody continued.

At landslide locations that disrupt the road surface, Dody added, the team is clearing material and securing the area so that vehicles can continue to pass. Meanwhile, at points that have the potential for further landslides or have experienced structural damage, the Public Works Ministry is preparing more permanent handling.

On the Ruteng–Reo–Kedindi section, for example, rock material covering the road area has been cleared. To anticipate subsequent landslides, follow-up handling is being prepared through the installation of rock bolts, wire mesh, and rockfall barriers. After emergency handling, traffic at the location remains functional in both directions.

Handling is also being carried out on the Ruteng–Km 210 and Km 210–Manggarai Regency Boundary sections. In addition to clearing landslide and rock material, the Public Works Ministry is installing warning signs, sealing cracks in the road surface and shoulders, cleaning drainage channels, and preparing slope reinforcement using rock bolts and safety nets at locations requiring permanent handling.

Meanwhile in the Ende area, handling is being carried out at several points on the Aegela–Ende City Boundary, Ende City Boundary–Detusoko, Junction–Wolowaru, and Wolowaru–Lianunu sections. Landslide clearing has been carried out, while affected road shoulders have been reinforced and several locations are being prepared for permanent handling in the form of retaining walls, shotcrete, active nets, and drainage systems to control water flow from slopes.

“The Public Works Ministry ensures that the condition of 15 national road sections affected by the earthquake remains generally functional. Vehicle flow, including logistics and fuel distribution, is also still running smoothly,” Dody concluded.

More from 23 August 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/a-week-after-flores-earthquake-public-works-ministry-handles-34-landslide-points-and-9-bridges-1787485892)
Originally published by Republika (https://ekonomi.republika.co.id/berita/tk7zpo370/sepekan-gempa-flores-kementerian-pu-tangani-34-titik-longsor-dan-9-jembatan), translated from Indonesian
Print