80% of Indonesia's Coal Is Low-Calorie, Unsuitable for Power Plants
The Minister of Energy and Mineral Resources (ESDM), Bahlil Lahadalia, has revealed that the majority of Indonesia’s current coal production is dominated by low to medium-calorie coal.
Meanwhile, high-calorie coal, which is widely needed for specific requirements including the blending of power plant fuels, is becoming increasingly scarce. He detailed that of the total national coal production, only about 20% possesses medium to high calorific value, ranging from 5,800 to 6,300 kcal/kg, while the remaining 80% consists of low-calorie coal.
“However, regarding the current situation, high-calorie coal is becoming scarcer by the day. From our 100% total coal production, the medium-grade coal above 5,800 to 6,300 kcal/kg does not exceed 20%. The remaining 80% is medium to low grade,” Bahlil stated at the Palace on Monday (22/06/2026).
Consequently, the government is preparing adjustment and modification measures in the management and utilisation of coal to ensure that energy supplies remain stable and the needs of power plants can be met. “Indeed, there must be modifications. We will regulate those modifications properly,” he added.
Previously, Bahluit disclosed that the issue causing rotational blackouts in several areas of Java was not actually related to the volume of supply, but rather the availability of medium-calorie coal required by PLN (the state electricity company) for the blending process of coal-fired power plant (PLTU) fuels.
“It turns out that what PLN is complaining about, or what PLN is requesting, is medium-calorie coal for blending. We have ensured that there is no longer a problem, and the government has assisted PLN to ensure operations can continue,” Bahlil said.
He further detailed that PLN’s coal requirement reaches approximately 154 million tonnes per year. Meanwhile, the Domestic Market Obligation (DMO) for coal supply assigned by the Ministry of ESDM to mining companies reaches approximately 180 to 190 million tonnes per year.
“PLN has contracted 134 million tonnes. In reality, the contract between PLN and entrepreneurs is for 134 million tonnes for one year. We are only in June, so there should be no issue,” Bahlil concluded.
Source: jawawa.id (https://jawawa.id/newsitem/80-of-indonesias-coal-is-low-calorie-unsuitable-for-power-plants-1782186746)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20260623100508-4-744916/tak-cocok-untuk-pembangkit-80-batu-bara-ri-berkalori-rendah), translated from Indonesian