        "msgid": "rapid-progress-peoples-school-construction-in-medan-already-above-70-percent-1779545628",
        "date": "2026-05-20 16:51:00",
        "title": "Rapid progress: People\u2019s School construction in Medan already above 70 percent",
        "author": "Cahya  Mulyana",
        "source": "MEDIA_INDONESIA",
        "tags": "",
        "topic": "Infrastructure",
        "summary": "PT Nindya Karya's chief commissioner Michael Umbas visited two Sekolah Rakyat sites in North Sumatra on 19 May to verify progress and boost the field teams. He highlighted that the Medan site is progressing rapidly and is already at 73.21% of its target (51.42%), with other locations also ahead of schedule; the project carries a contract value of about Rp1.2 trillion and targets completion by 20 June 2026. Umbas stressed that speed must be accompanied by quality and safety, and reaffirmed that Sekolah Rakyat is a flagship education programme under President Prabowo Subianto.",
        "content": "<p>PT Nindya Karya\u2019s chief commissioner, Michael Umbas, conducted field\nvisits to two Sekolah Rakyat (People\u2019s Schools) sites in North Sumatra \u2014\nin Deli Serdang and Medan \u2014 on Tuesday 19 May to ensure that works are\nprogressing as planned and to motivate the project teams on the ground.\nIn his briefing, he expressed appreciation for the progress achieved on\nthe Sekolah Rakyat in North Sumatra, noting the hard work, coordination\nand high commitment across the entire project team.<\/p>\n<p>He stressed the importance of maintaining the pace of construction,\nstrengthening cross\u2011sector coordination, and ensuring that quality and\nsafety remain top priorities until project completion.<\/p>\n<p>Specifically, Umbas praised the progress at the Medan site as highly\nsignificant and even a national benchmark: all roofing has been\ninstalled, most of the flooring is finished, ceilings are underway, and\nthe project is now in the final stages of MEP work \u2014 described as\nphenomenal.<\/p>\n<p>According to the M23 progress report, the overall North Sumatra SR\nprogramme is progressing positively and ahead of targets. At the\nlocation level, Medan has reached 73.21% of a target of 51.42%; Deli\nSerdang 55.22% of 50.74%; Serdang Bedagai 53.71% of 50.93%; South\nTapanuli 51.90% of 43.17%; and Padang Sidempuan 57.03% of 50.07%.<\/p>\n<p>Umbas indicated that these results demonstrate healthy acceleration\nand must be maintained through completion. \u201cThe most important thing is\nnot only to finish quickly, but also to ensure the quality of the\nbuildings, the functionality of the facilities, and that benefits are\ntruly felt by communities. Sekolah Rakyat is a visionary programme of\nPresident Prabowo Subianto that supports the future of the nation\u2019s\nyouth,\u201d he said.<\/p>\n<p>The Sekolah Rakyat project in North Sumatra forms part of a national\nstrategic education sector programme, with a contract value of around\nRp1.2 trillion and a completion target of 20 June 2026.<\/p>\n<p>As a national construction company, PT Nindya Karya reiterates its\ncommitment to continuing to support high\u2011quality educational\ninfrastructure as a tangible contribution to strengthening human\nresource development toward a Golden Indonesia.<\/p>\n<p>On-site in Deli Serdang, Umbas was accompanied by Project Manager\nDonny Kusuma. In Medan, he was accompanied by Project Manager Irwan\nFirmansyah. The visit to Medan was followed by a virtual conference with\nproject managers from across Sumatra.<\/p>",
        "url": "https:\/\/jawawa.id\/newsitem\/rapid-progress-peoples-school-construction-in-medan-already-above-70-percent-1779545628",