        "title": "Flood canal project hits a brick wall",
        "author": null,
        "source": "JP",
        "tags": null,
        "topic": null,
        "summary": "Flood canal project hits a brick wall Bambang Nurbianto, The Jakarta Post, Jakarta It is growing increasingly unlikely that the city administration will allocate the Rp 1.3 trillion (US$138,298) needed for clearing the 250 hectares of land for the East Flood Canal Project this year as expressed by city Governor Sutiyoso in February.",
        "content": "<p>Flood canal project hits a brick wall<\/p>\n<p>Bambang Nurbianto, The Jakarta Post, Jakarta<\/p>\n<p>It is growing increasingly unlikely that the city<br>\nadministration will allocate the Rp 1.3 trillion (US$138,298)<br>\nneeded for clearing the 250 hectares of land for the East Flood<br>\nCanal Project this year as expressed by city Governor Sutiyoso in<br>\nFebruary.<\/p>\n<p>Head of the city planning agency (Bapeda) Ritola Sasmaya said<br>\nhere on Saturday that the 2002 city budget for development<br>\nprojects was Rp 3.63 trillion, while the funds allocated for<br>\ndrainage and flood projects was only Rp 294.3 billion.<\/p>\n<p>\"If we have to spend Rp 1.3 trillion for the land clearance,<br>\nwe have to cut other development projects. But I'm not sure there<br>\nare any projects that could be canceled,\" Ritola said.<\/p>\n<p>The 23-kilometer long East Flood Canal project which is<br>\nestimated to cost about Rp 12 trillion is a joint project between<br>\nthe Central Government and the city administration as an effort<br>\nto solve the annual flood problem in the city.<\/p>\n<p>Sutiyoso said in February that the land clearance, which is<br>\nthe responsibility of the city administration, should be<br>\ncompleted this year to assure that the project construction,<br>\nwhich will be finalized within 10 years, could be started this<br>\nyear.<\/p>\n<p>Ritola said that financial constraints were not the only<br>\nproblem in implementing the land clearance as the land owners<br>\ndemanded that their lands should be priced much higher than the<br>\nTaxable Property Sale Value (NJOP).<\/p>\n<p>Ritola said that the city public works agency could only pay<br>\nthe owners 40 percent of the NJOP. But he said that there were<br>\ntwo regulations on the land clearance that contradicted each<br>\nother.<\/p>\n<p>\"One regulation says that the city should buy land from the<br>\npeople at the NJOP price. Another regulation says that the land<br>\nprice should be determined by negotiations with owners. That's<br>\nanother problem,\" he added.<\/p>\n<p>\"If the city allocates money for the land clearance, there<br>\nshould be a political decision (made by the city council and city<br>\nadministration),\" he added.<\/p>\n<p>The East Flood Canal is part of the government's plan to build<br>\na half-circle-like canal along the northern and eastern parts of<br>\nthe city that will function as a massive drain for the 13 rivers<br>\nhere, which originate in the highlands of Bogor and Depok in West<br>\nJava and empty into the Java Sea off North Jakarta.<\/p>\n<p>The other project is the 14-kilometer long West Flood Canal<br>\nconstructed in 1924 by the Dutch colonial government. That canal<br>\nneeds to be upgraded and properly maintained as it has fallen<br>\ninto disrepair in recent years.<\/p>\n<p>A feasibility study and design plan for the East Flood Canal<br>\nwas done by an Amsterdam-based consulting group, Nedeco, in 1976,<br>\nbut has not yet been acted upon, and since that time thousands of<br>\nhouses have been illegally built in the areas designated for the<br>\ncanal.<\/p>",
        "url": "https:\/\/jawawa.id\/newsitem\/flood-canal-project-hits-a-brick-wall-1447893297",
        "image": ""
    },
    "sponsor": "Okusi Associates",
    "sponsor_url": "https:\/\/okusiassociates.com"
}