        "title": "Final tenders for three power plants project approved",
        "author": null,
        "source": "JP",
        "tags": null,
        "topic": null,
        "summary": "Final tenders for three power plants project approved JAKARTA (JP): The government, after tough negotiations for half a year, has finally reached agreement with three consortia on the pricing of three major power projects planned to be established in Java at a total cost of US$1.67 billion. \"The new bidding prices reflect a 22-percent decline from $2.14 billion offered by the consortia in their first proposal to the state-owned electricity company PLN on Feb.",
        "content": "<p>Final tenders for three power plants project approved<\/p>\n<p>JAKARTA (JP): The government, after tough negotiations for<br>\nhalf a year, has finally reached agreement with three consortia<br>\non the pricing of three major power projects planned to be<br>\nestablished in Java at a total cost of US$1.67 billion.<\/p>\n<p>\"The new bidding prices reflect a 22-percent decline from<br>\n$2.14 billion offered by the consortia in their first proposal to<br>\nthe state-owned electricity company PLN on Feb. 15,\" Coordinating<br>\nMinister for Economy and Finance Saleh Afiff briefed some 50<br>\nreporters at his office here yesterday.<\/p>\n<p>Minister of Mines and Energy Ida Bagus Sudjana was present at<br>\nyesterday's briefing, which was also attended by Secretary<br>\nGeneral of the Ministry of Mines and Energy Umar Said, Director<br>\nGeneral for Electricity and New Energy Artono Arismunandar, PLN's<br>\npresident, Zuhal, and PLN's director for financial affairs,<br>\nRuswito.<\/p>\n<p>Saleh said that in its final offer on June 30, a consortium of<br>\nAsea Brown Boveri (ABB) of Switzerland and Marubeni Corp. of<br>\nJapan agreed to reduce its bidding price to $733.3 million for<br>\nconstruction of the 982-megawatt (MW) Muara Tawar combined-cycle<br>\npower project in West Java, as compared to $912.1 million it<br>\noffered on April 26.<\/p>\n<p>On the same date, the consortium of Japanese Sumitomo and<br>\nAmerican General Electric proposed a cost of $372 million for the<br>\nestablishment of a 505-MW combined-cycle power generation plant<br>\nin Tambak Lorok of Semarang, Central Java, as compared to the<br>\nprevious offer of $394 million.<\/p>\n<p>\"A group of Japan's Mitsubishi and German Siemens, meanwhile,<br>\noffered a cost of $571.1 million for construction of a combined-<br>\ncycle power generation plant with a capacity of 855 MW in Grati,<br>\nEast Java,\" he said. Previously, the Japanese-German consortium<br>\nproposed a $617.4-million cost for the Grati project, he added.<\/p>\n<p>Repeat-order<\/p>\n<p>The three projects, which will be set up under a repeat-order<br>\nbasis, were in limbo for half a year since it was offered to the<br>\nconsortia last November. Their offered prices in fact sparked<br>\nlong debates among business leaders and members of the House of<br>\nRepresentatives (DPR), most of whom came in conclusion that the<br>\nprices proposed by the consortia were too excessive.<\/p>\n<p>Saleh himself asked PLN some months ago to review the prices<br>\noffered by the consortia because they were \"still too high\", as<br>\ncompared to those in neighbor countries.<\/p>\n<p>President Soeharto even instructed PLN in February to open a<br>\nbidding for the three projects if the consortia were not ready to<br>\nlower their prices.<\/p>\n<p>On Feb. 26, the ABB-Marubeni consortium offered its price of<br>\n$744 million for the Muara Tawar project, down from its first<br>\noffer of $912.1 million on Feb. 15, the Sumitomo-General Electric<br>\ngroup offered $395 million for the Tambak Lorok plant, down from<br>\n$473.7 million and Mitsubishi-Siemens consortium offered  $630<br>\nmillion for Grati project from $761.2 million.<\/p>\n<p>Capacity<\/p>\n<p>Saleh said that during negotiations between the government and<br>\nthe ABB-Marubeni executives, the consortium was even committed to<br>\nincreasing the capacity of the planned Muara Tawar plant to<br>\n1,094.5 MW from the original plan of 982 MW.<\/p>\n<p>\"The Muara Tawar project will be even equipped with a new main<br>\nelectricity machine, which was not included in the previous<br>\noffer,\" he said.<\/p>\n<p>Zuhal, meanwhile, assured that the ABB-Marubeni consortium has<br>\nagreed to give three years in guarantee for the operation of the<br>\nmachine. An informed source close to the consortium told The<br>\nJakarta Post that the machine, called the 13E2 gas turbine<br>\nmachine, will be assembled in Germany.<\/p>\n<p>Saleh argued: \"If we calculate the total investment offered by<br>\nthe three consortia with the inclusion of the additional capacity<br>\noffered by the ABB-Marubeni consortium, the planned deals are 25<br>\npercent lower than the first offer of $540.6 million.\"<\/p>\n<p>Zuhal said the newly-approved prices are relatively lower than<br>\nthose offered for the construction of similar power plants in<br>\nMalaysia and Thailand.<\/p>\n<p>Both Saleh and Zuhal said that differences of prices in<br>\nforeign countries, among others, laid on their exclusion of local<br>\ncomponents, risk factors, terms of payment and cooling system<br>\nrequirements.<\/p>\n<p>With the approval of the government, Zuhal said, PLN is now<br>\npreparing to sign the three contracts. \"We expect that we can<br>\nsign the contracts in August,\" he said.<\/p>\n<p>He added that the construction of the open-cycle power plants<br>\nin Muara Tawar, Tambak Lorok and Grati will be completed within<br>\n17 months from the date of signing, while the construction of<br>\ntheir combined-cycle facilities will take 14 months after the<br>\ncompletion of the open-cycle plants. (fhp)<\/p>",
        "url": "https:\/\/jawawa.id\/newsitem\/final-tenders-for-three-power-plants-project-approved-1447893297",
        "image": ""
    },