        "title": "Bundaran HI underground project targeted for completion in June 2027",
        "author": "",
        "source": "ANTARA_ID",
        "tags": "",
        "topic": "Infrastructure",
        "summary": "Construction of the 4,439 square metre extended concourse beneath Bundaran HI has reached 24 percent progress as of August 2026, with completion targeted for June 2027 to coincide with Jakarta's 500th anniversary. The Rp148.2 billion project, undertaken by PT Integrasi Transit Jakarta, is Indonesia's first underground public space development. It is expected to improve connectivity between MRT, Transjakarta and surrounding commercial buildings while boosting visitor numbers by up to 6,000.",
        "content": "<p>The construction progress of the 4,439-square-metre underground\nmultifunctional space (extended concourse) at Bundaran HI reached 24\npercent in August 2026 and is targeted for completion in June 2027.<\/p>\n<p>The Extended Concourse project, undertaken by PT MRT Jakarta\n(Perseroda) through its subsidiary PT Integrasi Transit Jakarta (ITJ),\nis expected to be completed in time for Jakarta\u2019s 500th anniversary.<\/p>\n<p>\u201cThe target is for this to be a gift for Jakarta\u2019s five centuries and\nit will be inaugurated during the Jakarta anniversary celebrations,\u201d\nsaid ITJ President Director Ferdiansyah Roestam in Jakarta on\nTuesday.<\/p>\n<p>Ferdiansyah explained that the challenge in building the Extended\nConcourse as the first underground space project carried out in\nIndonesia is that there is no existing example to replicate.<\/p>\n<p>The Rp148.2 billion project is the first underground space\ndevelopment. If successful, it will certainly be followed by the\nconstruction of other extended concourses in Jakarta.<\/p>\n<p>\u201cWe have to read the building development maps in the Bundaran HI\narea and also read the underground cable maps and a number of other\nthings,\u201d said Ferdiansyah.<\/p>\n<p>According to him, this multifunctional space will have two access\npoints connected to existing buildings in the Bundaran HI area.<\/p>\n<p>The first access point is planned to be directly connected to Plaza\nIndonesia and Grand Hyatt. Meanwhile, the second access point will be\ndirectly connected to Wisma Nusantara and Hotel Pullman.<\/p>\n<p>This multifunctional space will also be connected to the Transjakarta\nbus stop at Bundaran HI via a lift.<\/p>\n<p>\u201cSo later Transjakarta users can access the extended concourse\ndirectly and be connected to the MRT Jakarta station,\u201d said\nFerdiansyah.<\/p>\n<p>He explained that this multifunctional space is located at a depth of\n18 metres below the roads of the Bundaran HI area, which is predicted to\nbecome a public gathering space for Jakarta residents.<\/p>\n<p>\u201cThis Extended Concourse is also a solution for pedestrians crossing\nfrom the east side to the west and vice versa. The public can also enjoy\nthis area as a transit space that certainly drives the economy,\u201d he\nsaid.<\/p>\n<p>The company predicts an increase in visitors of up to 6,000 people\nonce the underground multifunctional space is completed.<\/p>\n<p>The project is expected to become a new area that enlivens the\ntransit-oriented development (TOD) of Bundaran HI.<\/p>\n<p>\u201cWe hope to improve the comfort of public transport users while\nstrengthening connectivity in Jakarta\u2019s central business district,\u201d he\nsaid.<\/p>",
        "url": "https:\/\/jawawa.id\/newsitem\/bundaran-hi-underground-project-targeted-for-completion-in-june-2027-1787658859",